Define project; road project estimate

Short answer

A project is planned interrelated activities with clear objective, scope, time and budget. Road estimate uses survey/design data, quantities for earthwork, pavement, drainage, structures, protection and furniture, and District Rates with lead/lift. Abstract adds overhead/profit, 5% contingency, supervision, VAT 13%, land acquisition and utility shifting; report includes drawings, specs and programme.

Define project. Discuss estimation of a road project.

A project is a set of planned, interrelated activities with a clear objective, definite scope, limited time and a fixed budget. A road project is the construction (or upgrading) of a road of a defined standard between two points.

Estimation of a road project

  1. Survey and design data: reconnaissance and detailed survey, centre line, longitudinal section, cross-sections, traffic and soil (CBR) data, design standard (Nepal Road Standard 2070), drainage and structure design.
  2. Quantities are taken out from the drawings:
    • Earthwork in cutting and filling from cross-sections (mean-area or prismoidal method); rock excavation separately.
    • Sub-base, base course, wearing course (bituminous or concrete).
    • Drainage: side drains, culverts, causeways, bridges.
    • Protection works: retaining and breast walls, gabion, bio-engineering.
    • Road furniture: signs, kilometre stones, guard stones, markings.
  3. Rates from the District Rates and norms, with lead and lift for materials and plant (roller, grader, paver, tipper).
  4. Abstract of cost: the cost of all items is totalled; overhead and profit, physical contingency (5%), supervision and administration, environmental mitigation, price adjustment and VAT 13% are added.
  5. Report: introduction, design standards, quantities and rate analysis, abstract, specifications, drawings and construction programme.

Land acquisition and utility shifting are included as separate heads.