- 2076 Chaitra · 8 marks
T-beam decking quantities (6 m clear span)
Short answer
RCC (1:2:4) = 17.402 m³, wearing coat = 4.830 m³, total reinforcement = 2060.7 kg (2.5% steel in beams/fillets, 1% in slab/kerbs/posts), 40 mm G.I. pipe = 55.2 m.
Estimate the quantities of a T-beam decking of a single span bridge which has 6 m clear span and bearing on either side is 45 cm, from the accompanying bridge drawing. (Reinforcement: beam 2½%, slab and posts 1%.) [Figure: RCC T-beam decking cross-section. Overall width 7.7 m, 7 m roadway, 20×20 cm kerb on each side, 10 cm wearing coat of C.C., 20 cm slab, three ribs each 35 cm wide with 225 cm clear between ribs, rib depth below slab 75 cm (107.5 cm projections at the edges), 15×15 cm fillets, 15×15 cm RCC railing posts 120 cm high at 136 cm c/c, 40 mm dia G.I. pipe 4 nos., railing height 120 cm.]
Assumptions from the drawing
- Length of decking m (clear span plus bearing at both ends).
- Overhang of slab beyond outer ribs m (matches the 107.5 cm in the figure).
- Fillets are taken as triangles of 15 × 15 cm at both sides of each rib (6 in total). The railing posts are at 1.36 m c/c: with 6.90 m length this gives 6 posts per side, 12 in all.
- The 20 cm slab is taken from the figure; the kerb is 20 × 20 cm above the slab, and the wearing coat (10 cm) is laid between the kerbs over the 7.0 m roadway.
- Reinforcement as given: beams (ribs and fillets) 2.5%, slab and kerbs 1%, posts 1% of the volume of concrete; density of steel 7850 kg/m³.
- The railing has 4 lines of 40 mm G.I. pipe on each side, running the full length of the decking (assumption; the figure shows "4 nos").
Quantities
| Member | Working | Volume (m³) |
|---|---|---|
| Slab | 10.626 | |
| Ribs (3) | 5.434 | |
| Fillets (6, 15 × 15 cm triangular) | 0.466 | |
| Kerbs (2) | 0.552 | |
| Railing posts (12 nos, 15 × 15 × 120 cm) | 0.324 | |
| Total RCC (1:2:4) | 17.402 |
| Item | Working | Quantity |
|---|---|---|
| Wearing coat C.C. (1:2:4) | 4.830 m³ | |
| Steel in beams | 1,157.8 kg | |
| Steel in slab and kerbs | 877.5 kg | |
| Steel in posts | 25.4 kg | |
| Total steel | 2,060.7 kg | |
| G.I. pipe 40 mm dia. | 55.2 m |
Answer: RCC (1:2:4) = 17.402 m³; wearing coat = 4.830 m³; reinforcement = 2,060.7 kg; 40 mm G.I. pipe = 55.2 m.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- T-beam decking: RCC and wearing coat · Estimating and Costing, chapter 6 · asked 2×
- T-beam decking: PCC for RCC and steel · Estimating and Costing, chapter 6
- Bill of quantities for RCC T-beam bridge · Estimating and Costing, chapter 2
- RCC slab culvert 1.5 m span: four items · Estimating and Costing, chapter 6
- RCC slab culvert (u): four items · Estimating and Costing, chapter 6
- Materials for 12 cm RCC slab · Estimating and Costing, chapter 4
- Beam reinforcement for given loads, 6 m span · Design of RCC Structure, chapter 4
- Beam with torsion, 4.5 m clear span · Design of RCC Structure, chapter 5
- Staircase reinforcement drawing, effective span · Design of RCC Structure, chapter 9
- Beam supporting RCC slab, DL 25, IL 20 kN/m · Design of Steel and Timber Structure, chapter 7 · asked 2×