Bill of quantities for RCC T-beam bridge
Short answer
Bill of quantities lists each item with unit, quantity, rate and amount; amount equals quantity times rate. The T-beam decking works total Rs 6,557,220.00, comprising PCC Rs 1,425,600, formwork Rs 2,430,000, reinforcement Rs 2,484,000 and wearing coat Rs 217,620.
Prepare a bill of quantities from the following data for the construction of an RCC T-beam decking bridge.
| Quantity of work | Detail of work | Rate per unit of work |
|---|---|---|
| 108 m³ | PCC (1:1:2) for RCC works | Rs 13,200.00 |
| 3240 m² | Formwork for RCC works | Rs 750.00 |
| 21600 kg | Steel reinforcement for RCC works | Rs 115.00 |
| 18 m³ | PCC (1:2:4) wearing coat | Rs 12090.00 |
A bill of quantities lists each item with its description, unit, quantity, rate and amount (amount = quantity x rate).
| SN | Description of work | Unit | Quantity | Rate (Rs) | Amount (Rs) |
|---|---|---|---|---|---|
| 1 | PCC (1:1:2) for RCC works | m³ | 108 | 13,200.00 | 1,425,600.00 |
| 2 | Formwork for RCC works | m² | 3,240 | 750.00 | 2,430,000.00 |
| 3 | Steel reinforcement for RCC works | kg | 21,600 | 115.00 | 2,484,000.00 |
| 4 | PCC (1:2:4) wearing coat | m³ | 18 | 12,090.00 | 217,620.00 |
| Total | 6,557,220.00 |
Working of the amounts:
- PCC for RCC: 108 x 13,200 = 1,425,600.00
- Formwork: 3,240 x 750 = 2,430,000.00
- Reinforcement: 21,600 x 115 = 2,484,000.00
- Wearing coat: 18 x 12,090 = 217,620.00
Answer: Total cost of the T-beam decking works = Rs 6,557,220.00. Contingency and VAT are added to this total if required.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- T-beam decking: PCC for RCC and steel · Estimating and Costing, chapter 6
- T-beam decking: RCC and wearing coat · Estimating and Costing, chapter 6 · asked 2×
- T-beam decking quantities (6 m clear span) · Estimating and Costing, chapter 6
- Prepare AOC, BOQ and summary of cost · Estimating and Costing, chapter 2
- Rate analysis: M20 (1:1½:3) RCC per 10 m³ · Estimating and Costing, chapter 4
- Rate analysis: PCC 1:3:6 per m³ · Estimating and Costing, chapter 4
- Contractor asks supervisor to prepare running bill · Engineering Professional Practice, chapter 7
- EVA; 60 days, 25% work, Rs 12,00,000 · Project Engineering, chapter 4
- EVA and S-curve; Rs 30,00,000, 24 months · Project Engineering, chapter 4
- EVA application; 35 days, Rs 8,00,000 spent · Project Engineering, chapter 4