- 2075 Ashwin · 3 marks
Forebay dimension for 3 minutes storage
Short answer
Volume = 3600 m³, area = 100 m², depth 8.4 m. Dimensions: 36 m long × 12 m wide × 8.4 m deep.
Find out the dimension of a forebay which accommodates a storage for 3 minutes of operation for a hydropower plant having the following data: design discharge = 20 m³/s; length of penstock = 300 m; diameter of penstock = 2.20 m.
Given: m³/s; 1 penstock (assumed) of diameter 2.2 m and length 300 m; storage (retention) time 3 min; limiting velocity in the forebay 0.20 m/s (assumed, the usual limit, as it is not given).
Step 1: Volume of the forebay
The forebay stores the water for the retention time:
Step 2: Cross-sectional area from the velocity limit
Step 3: Depth of water (submergence of the penstock intake)
Velocity in the penstock: m/s. Minimum submergence to avoid vortices (Gordon, with for an asymmetrical approach, which is on the safe side):
Water depth = bottom clearance of 0.5 m m, adopt m.
Step 4: Width and length
Adopt m and m (the volume is then m³ ).
The penstock length (300 m) is not needed to size the forebay by this method; it matters for the penstock head loss and the water hammer.
PLAN
headrace forebay penstock
tunnel/canal +------------------+
====> \ | |
\ trans| trash rack |==> penstock
====> / | |
+--+-spillway-+-flush+
| |
v v to river (spillway/flushing)
SECTION
canal bed ____ WL ~~~~~~~~~~~~~~~~~~~~~~
| S (submergence)
| rack ____ crown
| #### \ penstock
flushing ______ |___####____\_D__
bottom clearance 0.5 m
| Item | Value |
|---|---|
| Storage volume | 3600 m³ |
| Water depth | 8.4 m (+0.5 m free board) |
| Width | 12.0 m |
| Length | 36 m |
| Submergence of penstock crown | 5.65 m |
Answer: forebay about 36 m long x 12.0 m wide x 8.4 m deep (water), with a volume of 3600 m³.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Forebay design (20 m³/s, 300 m penstock) · Hydropower Engineering, chapter 6
- Forebay design (15 m³/s, 4 minutes) · Hydropower Engineering, chapter 6
- Forebay design with spillway length (14 m³/s) · Hydropower Engineering, chapter 6
- Forebay design considerations; design for 12 m³/s · Hydropower Engineering, chapter 6
- Forebay design (14.5 m³/s, two penstocks) · Hydropower Engineering, chapter 6
- Economic diameter; penstock thickness (1.25 m) · Hydropower Engineering, chapter 6
- Design: 300 m head plant, GCB rating · Power Plant Design, chapter 4 · asked 11×
- Operation of pumped storage hydro plant · Power Plant Equipment, chapter 1 · asked 2×
- Steady state operation of hydropower plant · Power Plant Equipment, chapter 1
- Design: 230 m head plant, 20 km line · Power Plant Design, chapter 4 · asked 14×