Francis size and setting (150 m, 160 m³/s)

Short answer

Use 4 units of 50 MW; speed 230.8 rpm, runner diameter about 3.14 m; setting height is at most about 3.8 m above tailwater.

Determine the size and setting height of the Francis turbine for a site having net head of 150 m, discharge is 160 m³/s and efficiency of 85%.

Step 1: Power and units

P=ηγQH=0.85×9.81×160×150=200,124 kWP = \eta\gamma Q H = 0.85 \times 9.81 \times 160 \times 150 = 200{,}124\ \text{kW}

Number of units: adopt 4 units, each Q=40Q = 40 m³/s and Pu=50,031P_u = 50{,}031 kW.

Step 2: Specific speed and rated speed

For Francis turbines (metric units, kW, m, rpm) the empirical relation of Schweiger and Gregory is

Ns=3763H0.854+49.4=101.5N_s = \frac{3763}{H^{0.854}} + 49.4 = 101.5 N=NsH5/4Pu=238.3 rpmN = \frac{N_s H^{5/4}}{\sqrt{P_u}} = 238.3\ \text{rpm}

Synchronous speed at 50 Hz: N=6000/pN = 6000/p. Adopt p=26p = 26 poles, N=230.8N = 230.8 rpm. Actual specific speed:

Ns=NPuH5/4=98.3N_s = \frac{N\sqrt{P_u}}{H^{5/4}} = 98.3

Step 3: Runner diameter

Peripheral speed u=Ku2gHu = K_u\sqrt{2gH} with Ku=0.7K_u = 0.7 (range 0.6 to 0.9):

u=0.72×9.81×150=37.97 m/s,D=60uπN=60×37.97π×230.8=3.14 mu = 0.7\sqrt{2 \times 9.81 \times 150} = 37.97\ \text{m/s}, \qquad D = \frac{60u}{\pi N} = \frac{60 \times 37.97}{\pi \times 230.8} = 3.14\ \text{m}

Step 4: Setting (Thoma cavitation coefficient)

σc=0.0432(Ns100)2=0.0418\sigma_c = 0.0432\left(\frac{N_s}{100}\right)^2 = 0.0418

Sea-level site assumed: Hatm=10.3H_{atm} = 10.3 m, Hv=0.24H_v = 0.24 m.

Hs=Hatm−Hv−σcH=10.3−0.24−0.0418×150=3.79 mH_s = H_{atm} - H_v - \sigma_c H = 10.3 - 0.24 - 0.0418 \times 150 = 3.79\ \text{m}

This is the highest permissible level of the runner outlet above tailwater; in practice set lower (safety margin 1 to 2 m, and reduce HatmH_{atm} by about 1 m per 900 m of site elevation).

Answer: 4 units of 50 MW; N=230.8N = 230.8 rpm; runner diameter D≈3.14D \approx 3.14 m; setting height Hs≤3.8H_s \le 3.8 m above tailwater level.