Common RoR intakes in Nepal; site selection

Short answer

Common intakes in Nepal are side intakes (most common) and bottom (Tyrolean) intakes for steep streams. Site selection factors: outer bank of a stable bend, good foundation, sufficient head for gravity flow, away from sediment zones, good access, narrow section for weir, flood safety, and minimal environmental impact.

What are the most commonly used intakes in Run-of-River projects in Nepal? What factors do you consider while selecting the site for intake location?

Intakes commonly used in RoR projects in Nepal

  1. Side intake: an opening in the river bank, with a trash rack and gate, built at the side of the weir and undersluice. It is the most common type in Nepal because the river carries a large bed load and the flow can be diverted with simple structures.
  2. Bottom (Tyrolean / drop) intake: a trench with a rack across the river bed in steep, boulder-carrying streams; water drops through the bars into a collection chamber (used in small hydropower and micro-hydro projects in the hills).
  3. Frontal intake: an opening at the front of the weir facing the flow (less common because it takes much bed load).

Factors for selecting the intake location

  • Outer (concave) bank of a stable river bend, where the secondary current moves bed load away from the intake; or a straight stable reach.
  • Stable river reach and good foundation: rock or firm soil; no active landslide or erosion.
  • Sufficient head and level to give gravity flow to the settling basin and headrace without long canals.
  • Away from sediment deposition zones, confluences of tributaries and high debris areas.
  • Good access for construction, operation and maintenance.
  • Cheap river training and weir construction: a narrow section where the weir is short, and enough space for the gravel trap and settling basin close by.
  • Flood safety: high flood level, minimal flood damage to the headworks and powerhouse.
  • Environmental and social: minimum effect on existing water users, fish and forest.