- 2074 Ashwin · 3+3+4 marks
RoR and PRoR from hydrograph equation (Q40)
Short answer
(a) RoR: installed capacity = 116.2 MW, firm energy = 255.2 GWh. (b) PRoR: installed capacity = 232.4 MW.
The hydrograph of a typical river of Nepal follows the equation , where is the mean monthly discharge in m³/s and is time in months counted with October as the 1st month and so on. A hydropower plant has to be developed in this river with net head of 150 m and overall efficiency of 85%; the environmental flow is not considered. a) Calculate the installed capacity and firm energy for the RoR project that will be developed for design discharge . b) If the project has to be designed as a Peaking Run of the River (PRoR) project for 6 hrs daily peaking (3 hrs in morning and 3 hrs in evening) and with design discharge , what is the installed capacity of the PRoR project? Assume that the project is designed in such a way that 50% of the available flow is used during the off-peak hours and the remaining 50% of the available flow is stored for peak hour generation. Neglect all the losses.
Monthly flows from
| t | Month | Q (m³/s) |
|---|---|---|
| 1 | Oct | 94.25 |
| 2 | Nov | 59.75 |
| 3 | Dec | 36.42 |
| 4 | Jan | 24.26 |
| 5 | Feb | 23.29 |
| 6 | Mar | 33.49 |
| 7 | Apr | 54.88 |
| 8 | May | 87.44 |
| 9 | Jun | 131.17 |
| 10 | Jul | 186.09 |
| 11 | Aug | 252.18 |
| 12 | Sep | 329.46 |
m, : kW per m³/s.
Design discharge
Descending flows: 329.46, 252.18, 186.09, 131.17, 94.25, 87.44, 59.75, 54.88, 36.42, 33.49, 24.26, 23.29. Weibull position for 40%: (between the 5th flow 94.25 and the 6th flow 87.44):
a) RoR project
The minimum monthly flow is 23.29 m³/s (February), the flow available in all months, so
(Total energy with flows limited to is 715.8 GWh; the part above firm energy is secondary energy.)
b) Peaking run-of-river (6 h daily peaking)
Daily water volume at : . Half of it (50%) is used during the 18 off-peak hours and the other half is stored (pond volume m³) and used in the 6 peak hours:
Off-peak the plant uses m³/s. The installed capacity is therefore twice that of the RoR plant.
Answer: (a) RoR: installed capacity = 116.2 MW, firm energy = 255.2 GWh; (b) PRoR: installed capacity = 232.4 MW.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- RoR at 40% exceedence; storage regulation · Hydropower Engineering, chapter 3
- Load duration curve; diesel plant; ROR flow duration · Hydropower Engineering, chapter 3
- Peaking RoR: max power and wet/dry energy ratio · Hydropower Engineering, chapter 3
- Working principle of RoR, PRoR and ST plants · Hydropower Engineering, chapter 2
- RoR capacity, peaking capacity and benefit · Hydropower Engineering, chapter 3
- RoR best installed capacity (USD 2795 million) · Hydropower Engineering, chapter 3
- Design: 589 m head plant at Q40% · Power Plant Design, chapter 4 · asked 3×
- ROR versus PROR hydropower plants · Power Plant Design, chapter 3
- Sketch of a medium head PROR plant · Power Plant Design, chapter 3 · asked 2×
- Design: 300 m head plant, GCB rating · Power Plant Design, chapter 4 · asked 11×