RoR and PRoR from hydrograph equation (Q40)

Short answer

(a) RoR: installed capacity = 116.2 MW, firm energy = 255.2 GWh. (b) PRoR: installed capacity = 232.4 MW.

The hydrograph of a typical river of Nepal follows the equation Qt=5.589t2−51.275t+139.94Q_t = 5.589t^2 - 51.275t + 139.94, where QtQ_t is the mean monthly discharge in m³/s and tt is time in months counted with October as the 1st month and so on. A hydropower plant has to be developed in this river with net head of 150 m and overall efficiency of 85%; the environmental flow is not considered. a) Calculate the installed capacity and firm energy for the RoR project that will be developed for design discharge Q40Q_{40}. b) If the project has to be designed as a Peaking Run of the River (PRoR) project for 6 hrs daily peaking (3 hrs in morning and 3 hrs in evening) and with design discharge Q40Q_{40}, what is the installed capacity of the PRoR project? Assume that the project is designed in such a way that 50% of the available flow is used during the off-peak hours and the remaining 50% of the available flow is stored for peak hour generation. Neglect all the losses.

Monthly flows from Qt=5.589t2−51.275t+139.94Q_t = 5.589t^2 - 51.275t + 139.94

tMonthQ (m³/s)
1Oct94.25
2Nov59.75
3Dec36.42
4Jan24.26
5Feb23.29
6Mar33.49
7Apr54.88
8May87.44
9Jun131.17
10Jul186.09
11Aug252.18
12Sep329.46

H=150H=150 m, η=0.85\eta=0.85: 9.81 η H=1250.779.81\,\eta\,H = 1250.77 kW per m³/s.

Design discharge Q40Q_{40}

Descending flows: 329.46, 252.18, 186.09, 131.17, 94.25, 87.44, 59.75, 54.88, 36.42, 33.49, 24.26, 23.29. Weibull position for 40%: m=0.4×13=5.2m=0.4\times13=5.2 (between the 5th flow 94.25 and the 6th flow 87.44):

Q40=94.25−0.2 (94.25−87.44)=92.89 m3/sQ_{40} = 94.25 - 0.2\,(94.25-87.44) = 92.89\ \text{m}^3/\text{s}

a) RoR project

P=1250.77×92.89=116,185 kW=116.18 MWP = 1250.77\times92.89 = 116,185\ \text{kW} = 116.18\ \text{MW}

The minimum monthly flow is 23.29 m³/s (February), the flow available in all months, so

Efirm=1250.77×23.29×8760=255,183,616 kWh=255.2 GWhE_{firm} = 1250.77\times23.29\times8760 = 255,183,616\ \text{kWh} = 255.2\ \text{GWh}

(Total energy with flows limited to Q40Q_{40} is 715.8 GWh; the part above firm energy is secondary energy.)

b) Peaking run-of-river (6 h daily peaking)

Daily water volume at Q40Q_{40}: Q40×24×3600Q_{40}\times24\times3600. Half of it (50%) is used during the 18 off-peak hours and the other half is stored (pond volume =0.5×92.89×86400=4,012,865=0.5\times92.89\times86400=4,012,865 m³) and used in the 6 peak hours:

Qpeak=0.5 Q40×246=2 Q40=185.78 m3/sQ_{peak} = \frac{0.5\,Q_{40}\times24}{6} = 2\,Q_{40} = 185.78\ \text{m}^3/\text{s} PPRoR=1250.77×185.78=232,370 kW=232.37 MWP_{PRoR} = 1250.77\times185.78 = 232,370\ \text{kW} = 232.37\ \text{MW}

Off-peak the plant uses 0.5 Q40×24/18=61.930.5\,Q_{40}\times24/18 = 61.93 m³/s. The installed capacity is therefore twice that of the RoR plant.

Answer: (a) RoR: installed capacity = 116.2 MW, firm energy = 255.2 GWh; (b) PRoR: installed capacity = 232.4 MW.