RoR at 40% exceedence; storage regulation

Short answer

(i) P = 683.8 MW, spill energy ≈ 3165 GWh, firm energy = 730.5 GWh. (ii) Storage required = 12,369 Mm³. (iii) P = 769.9 MW, annual energy = 6745 GWh.

A hydropower project is planned to develop in a river having net head of 100 m and overall efficiency of 85% with the monthly hydrograph as shown below.

MonthJanFebMarAprMayJunJulAugSepOctNovDec
Discharge (m³/s)1001201403003201800200025002100900500300

i) Calculate the installed capacity, annual spill energy and firm energy if the RoR project is designed based on the 40% probability of exceedence flow. ii) If the storage project is developed with full regulation of the annual hydrograph (design discharge is equal to the average monthly flow), calculate the storage requirements. iii) Calculate the installed capacity and annual energy generation from the storage project as mentioned in the above case.

Data

H=100H=100 m, η=0.85\eta=0.85, so 9.81 η H=833.859.81\,\eta\,H = 833.85 kW per m³/s. One month =730=730 h =2.628×106=2.628\times10^6 s.

i) RoR designed for Q40Q_{40}

Flows in descending order: 2500, 2100, 2000, 1800, 900, 500, 320, 300, 300, 140, 120, 100. By the Weibull formula p=mN+1×100p=\frac{m}{N+1}\times100 with N=12N=12, p=40%p=40\% gives m=0.4×13=5.2m=0.4\times13=5.2, which lies between 900 (m = 5) and 500 (m = 6):

Q40=900−0.2 (900−500)=820 m3/sQ_{40} = 900 - 0.2\,(900-500) = 820\ \text{m}^3/\text{s} P=833.85×820=683,757 kW=683.8 MWP = 833.85\times820 = 683,757\ \text{kW} = 683.8\ \text{MW}
  • Spill (flow above Q40Q_{40}) by month (m³/s): Jun 980, Jul 1180, Aug 1680, Sep 1280, Oct 80, total =5,200=5,200 m³/s-months.
Espill=833.85×5,200×730=3,165 GWhE_{spill} = 833.85\times5,200\times730 = 3,165\ \text{GWh}
  • Firm energy (minimum flow 100 m³/s available all year):
Efirm=833.85×100×8760=730.5 GWhE_{firm} = 833.85\times100\times8760 = 730.5\ \text{GWh}
  • (Total energy of the RoR plant =833.85×5,880×730=3,579= 833.85\times5,880\times730 = 3,579 GWh, so the non-firm energy is 2,849 GWh.)

ii) Storage with full regulation

The design discharge equals the mean flow:

Qˉ=11,08012=923.33 m3/s\bar Q = \frac{11,080}{12} = 923.33\ \text{m}^3/\text{s}

Deficits (Qˉ−Q\bar Q-Q) in the months with flow below the mean, from Oct to May (m³/s-months): Oct 23.33, Nov 423.33, Dec 623.33, Jan 823.33, Feb 803.33, Mar 783.33, Apr 623.33, May 603.33. Sum =4,706.67=4,706.67 (this equals the surplus of Jun-Sep, which refills the reservoir).

Vs=4,706.67×2.628×106=12,369×106 m3≈12.37 billion m3V_s = 4,706.67\times2.628\times10^6 = 12,369\times10^6\ \text{m}^3 \approx 12.37\ \text{billion m}^3

iii) Installed capacity and energy of the storage project

P=833.85×923.33=769,922 kW=769.9 MWP = 833.85\times923.33 = 769,922\ \text{kW} = 769.9\ \text{MW} E=P×8760=6,745 GWh/yearE = P\times8760 = 6,745\ \text{GWh/year}

(The head is taken as constant at 100 m.)

Answer: (i) P = 683.8 MW at Q40=820Q_{40}=820 m³/s; spill energy ≈ 3,165 GWh; firm energy = 730.5 GWh. (ii) storage = 12,369 Mm³. (iii) P = 769.9 MW; E = 6,745 GWh.