- 2070 Chaitra · 2+2+2+2+2+2 marks
RoR at 40% exceedence; storage regulation
Short answer
(i) P = 683.8 MW, spill energy ≈ 3165 GWh, firm energy = 730.5 GWh. (ii) Storage required = 12,369 Mm³. (iii) P = 769.9 MW, annual energy = 6745 GWh.
A hydropower project is planned to develop in a river having net head of 100 m and overall efficiency of 85% with the monthly hydrograph as shown below.
| Month | Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Discharge (m³/s) | 100 | 120 | 140 | 300 | 320 | 1800 | 2000 | 2500 | 2100 | 900 | 500 | 300 |
i) Calculate the installed capacity, annual spill energy and firm energy if the RoR project is designed based on the 40% probability of exceedence flow. ii) If the storage project is developed with full regulation of the annual hydrograph (design discharge is equal to the average monthly flow), calculate the storage requirements. iii) Calculate the installed capacity and annual energy generation from the storage project as mentioned in the above case.
Data
m, , so kW per m³/s. One month h s.
i) RoR designed for
Flows in descending order: 2500, 2100, 2000, 1800, 900, 500, 320, 300, 300, 140, 120, 100. By the Weibull formula with , gives , which lies between 900 (m = 5) and 500 (m = 6):
- Spill (flow above ) by month (m³/s): Jun 980, Jul 1180, Aug 1680, Sep 1280, Oct 80, total m³/s-months.
- Firm energy (minimum flow 100 m³/s available all year):
- (Total energy of the RoR plant GWh, so the non-firm energy is 2,849 GWh.)
ii) Storage with full regulation
The design discharge equals the mean flow:
Deficits () in the months with flow below the mean, from Oct to May (m³/s-months): Oct 23.33, Nov 423.33, Dec 623.33, Jan 823.33, Feb 803.33, Mar 783.33, Apr 623.33, May 603.33. Sum (this equals the surplus of Jun-Sep, which refills the reservoir).
iii) Installed capacity and energy of the storage project
(The head is taken as constant at 100 m.)
Answer: (i) P = 683.8 MW at m³/s; spill energy ≈ 3,165 GWh; firm energy = 730.5 GWh. (ii) storage = 12,369 Mm³. (iii) P = 769.9 MW; E = 6,745 GWh.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Full regulation: reservoir, capacity, annual energy · Hydropower Engineering, chapter 3
- RoR and PRoR from hydrograph equation (Q40) · Hydropower Engineering, chapter 3
- RoR best installed capacity (NRs, 45 years) · Hydropower Engineering, chapter 3
- RoR capacity, peaking capacity and benefit · Hydropower Engineering, chapter 3
- RoR best installed capacity (USD 2795 million) · Hydropower Engineering, chapter 3
- Peaking RoR: max power and wet/dry energy ratio · Hydropower Engineering, chapter 3
- Short line 40 km, 381 MVA: regulation and efficiency · Power System Analysis I, chapter 6
- Annual firm and secondary energy (900 m³/s, Nov 100) · Hydro Power, chapter 3 · asked 2×
- Regulation and efficiency of 100 km, 110 kV line · Power System Analysis I, chapter 6 · asked 2×
- Primary and secondary energy with 10% environmental flow · Hydro Power, chapter 3