- 2072 Kartik · 2+3+3 marks
Development stages and PRoR working principle
Short answer
A PRoR plant has a weir with a small pond storing river flow for hours. In dry season, off-peak water is stored; peak hours stored water plus inflow run turbines at full capacity. In wet season it acts as RoR. Components: weir, intake, gravel trap, pond, desander, headrace tunnel, surge tank, penstock, powerhouse, tailrace.
What are the different stages of hydropower development? Explain the working principle of a peaking run-of-river plant and show the general arrangement of components with neat sketches.
Stages of hydropower development
- Reconnaissance study
- Pre-feasibility study
- Feasibility study
- Detailed engineering design and tender
- Construction and commissioning
- Operation and maintenance
Working principle of a peaking run-of-river (PRoR) plant
A PRoR plant has a weir plus a small reservoir (pond) at the headworks that can store the river flow for several hours. In the dry season the river flow is small. During the off-peak hours the turbines run at low load or stop, and the water is stored in the pond. In peak hours (usually 4-6 hours in the morning and evening) the stored water plus the inflow runs the turbines at full load. In the wet season, when flow is large, it behaves as an ordinary RoR plant. So the installed capacity is larger than for a pure RoR plant, and the energy has a higher value because it is supplied at peak time. Examples are Kaligandaki A and Upper Tamakoshi.
General arrangement of components
River --> Weir + Undersluice --> Intake --> Gravel trap
| |
Pond (daily) Desander
|
Headrace tunnel
|
Surge tank
|
Penstock
|
Powerhouse --> Tailrace --> River
Section
FSL ~~~~~|weir intake====tunnel====(ST)
MDDL ~~~~|pond \ penstock
\__PH
Fluctuating pond level between FSL and MDDL gives the daily storage.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Working principle of RoR, PRoR and ST plants · Hydropower Engineering, chapter 2
- Stages of hydropower development cycle · Hydropower Engineering, chapter 2
- RoR and PRoR from hydrograph equation (Q40) · Hydropower Engineering, chapter 3
- Powerhouse general arrangement and dimensions · Hydropower Engineering, chapter 8 · asked 3×
- RoR capacity, peaking capacity and benefit · Hydropower Engineering, chapter 3
- RoR headworks arrangement and functional requirements · Hydropower Engineering, chapter 5 · asked 3×
- Components of a run-of-river plant · Power Plant Design, chapter 3 · asked 2×
- Schematic of a PROR hydropower plant · Power Plant Design, chapter 3 · asked 2×
- Daily pondage run-of-river components · Power Plant Design, chapter 3
- ROR versus PROR hydropower plants · Power Plant Design, chapter 3