- 2079 Baisakh · 1+2+3 marks
Cost control and cost control cycle
Short answer
Cost control keeps actual cost within budget by recording, comparing, analysing variances, and correcting. The cycle is budget baseline, record actual cost, compare, analyse variance, forecast EAC, take corrective action, update. Methods include cost codes, variance analysis, earned value (CV, CPI, EAC), S-curves, change control, material control, productivity improvement, and time-cost trade-off.
Discuss cost control, cost control cycle and methods of cost control in brief.
Cost control
Cost control is the process of keeping the actual cost of the project within the approved budget by recording costs, comparing them with the budget, finding the variances and taking corrective action.
Cost control cycle
Budget baseline -> Record actual cost -> Compare with budget
^ |
| v
Update budget <- Corrective action <- Analyse variance
and forecast cost
- Prepare the budget baseline from the WBS and cost codes.
- Record the actual costs (labour, material, equipment) from bills and site records.
- Compare actual with budgeted (earned) cost and find the variance.
- Analyse the causes and forecast the final cost (EAC).
- Take corrective action; revise the budget through approved changes; repeat.
Methods of cost control
- Cost budgeting and cost codes by WBS, with a responsible person for each item.
- Variance analysis and exception reports (actual against budget).
- Earned value analysis: CV, CPI and EAC.
- S-curve and cash flow control of planned against actual expenditure.
- Control of changes and variation orders; claims management.
- Procurement and material control: bulk buying, store control, reducing wastage.
- Productivity improvement, better equipment use, and work study.
- Time-cost trade-off (crashing only when the benefit is greater) and value engineering.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Monitoring and quality, cost, schedule control · Project Engineering, chapter 4
- Elements of cost control; feedback control · Project Engineering, chapter 4
- Cost control need; earned value; EVA approach · Project Engineering, chapter 4
- Cost control; EVA 50 doghouses in 90 days · Project Engineering, chapter 4
- Cost control; EVA 15 houses in 3 months · Project Engineering, chapter 4
- Monitoring, evaluation, control; control cycle · Project Engineering, chapter 4 · asked 4×
- Short note: Cost control · Construction Management, chapter 7
- First law for control mass; cycle; power and refrigeration · Fundamental of Thermodynamics & Heat Transfer, chapter 4
- Test life cycle in quality control · ICT Project Management, chapter 10
- AC voltage controller on-off cycle control numerical · Power Electronics, chapter 6