Define, classify project; temporary organization

Short answer

A project is a temporary endeavor with definite start and end, creating a unique product within constraints. Classification by sector, size, ownership, resources, participation, purpose, technology, time, location. Characteristics: specific objective, definite life, uniqueness, progressive elaboration, temporary team, limited resources, uncertainty, interdependent tasks. Temporary team: formed from different fields, disbands after completion (e.g., district hospital team dissolves after handover).

Define a project and classify it. Name the characteristics of a project and describe what you mean by a temporary team/organization in a project.

Definition

A project is a temporary endeavour, with a definite start and end, undertaken by a team to create a unique product, service or result within limited time, cost and quality constraints. Examples: building the Kathmandu-Terai Fast Track, a 100 MW hydropower plant, a bridge, or developing a hospital information system.

Classification

BasisTypesExample
SectorAgriculture, industry, energy, transport, health, educationIrrigation canal, cement factory
Size / costSmall, medium, large, megaFoot trail vs Melamchi water project
OwnershipPublic, private, public-private (PPP)Government road, private hotel, BOOT hydropower
Nature of resourcesLabour intensive, capital intensiveRural road by user groups, a dam
ParticipationDomestic, bilateral, multilateral, joint ventureGovernment-funded road, Pokhara Airport (China Exim loan), ADB-funded water supply, Khimti hydropower
PurposeProduction, service, infrastructure, socialFactory, school, bridge
TechnologyConventional, high technologyManual brick kiln vs automated plant
TimeShort term, medium term, long term6-month school building vs 10-year highway
LocationUrban, rural, regional, nationalSmart city, village water supply

Characteristics

  • Specific objective
  • Definite life span
  • Unique, non-routine task
  • Progressive elaboration
  • Temporary team
  • Limited resources
  • Uncertainty and risk
  • Interdependent activities

Temporary team / organisation

A project needs people from different fields for a limited time. A team is formed when the project starts: the project manager is appointed, and engineers, surveyors, accountants and workers are drawn from the parent organisation or hired from outside. Once the project is completed, the team is disbanded and the members return to their departments or move to other projects.

Features: it is created for one objective, has a leader with clear authority, its members bring different skills, and it has no permanent status. Example: the team formed to build a district hospital, which dissolves after handover. Because the group is new, team building, role definition and communication are essential.

✓ Answer checked by Claude Opus 5.5 (high effort)