- 2076 Chaitra · 8 marks
Flexible pavement life with 140 cvpd traffic
Short answer
Using AASHTO, subgrade CBR 5 % (90th percentile) and structural number 3.37 give a capacity of 0.79 million ESAL. With vehicle damage factor 1.90, opening traffic 157 cvpd (8 % growth, 1.5-year construction), solving the traffic equation yields a pavement life of 5.9 years.
A proposed flexible pavement design of single lane carriageway consists of 75mm of Asphalt concrete, 120 mm of emulsified stabilized base course and 145mm of granular subbase. The expected commercial traffic volume is 140 cvpd. The expected traffic composition is 30% truck, 30% of mini truck and 40% of bus, whose truck factors are 5.6, 0.6 and 0.1 respectively. The expected annual traffic growth rate is 8% for all vehicles, and 18month required for construction to be completed. The CBR test conducted at 7 locations strating from Ch.0+100 at the interval of 200m distance gave the value of 11,9,7,10,8,6,4. E_sub base=275 MPa, E_base=500MPa and E_surface=2400 MPa. How many years can this pavement last?
Approach
The structure is given, so its capacity (ESAL) is found with the layer-coefficient (structural number) method of AASHTO, then divided by the yearly traffic to get the life. Assumed: reliability 90 % (), , , drainage coefficients , single lane so the design lane takes 100 percent of traffic.
Step 1 - Subgrade
CBR values at 7 locations: 11, 9, 7, 10, 8, 6, 4. The 90th percentile value (90 percent equal or greater) lies between 4 % (100 percent) and 6 % (85.7 percent) and is about 5.4 %; adopt CBR = 5 %, MPa psi.
Step 2 - Layer coefficients (E in psi)
Step 3 - Structural number of the section
Step 4 - ESALs the pavement can carry
With and psi in the AASHTO-93 equation: , so ESAL ( million).
Step 5 - Traffic per year
VDF from truck factors: . Traffic at opening (18 months of construction): CVPD.
Answer: the pavement will last about 5.9 years after opening (CBR 5 %, SN = 3.37, capacity 0.79 million ESAL).
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Flexible design: 4-lane single carriageway, 2000 CVPD · Transportation Engineering II, chapter 2
- VDF; four-lane flexible design from catalogue · Transportation Engineering II, chapter 2
- Asphalt Institute design: 1850 ESA/day four lane · Transportation Engineering II, chapter 2
- IRC pavement design: 5640 CVPD, CBR 6% · Transportation Engineering II, chapter 2
- Asphalt Institute design: 5.11×10⁴ ESAL/year, 12 years · Transportation Engineering II, chapter 2
- Flexible pavement design: four lane, ADT 8000 trucks · Transportation Engineering II, chapter 2