Webster two-phase signal with saturation headways

The design hour traffic and saturation headway at a four-legged intersection are:

ApproachNorth (N)South (S)East (E)West (W)
Design hour flow450430350315
Saturation headway (sec)2.252.332.52.75

Design a two phase signal for the intersection based on Webster method and draw the phase diagram. Use amber time of 2 sec on each phase for clearance and start-up loss time phase per phase of 1.5 sec.

Phases: Phase 1 = North-South, Phase 2 = East-West. Saturation flow from saturation headway s=3600/hs = 3600/h.

Step 1: Flow ratios

Flow ratio y=q/sy = q/s for each approach; the larger value in a phase is the critical one.

PhaseApproachqsy = q/s
Phase 1North45016000.281 (critical)
Phase 1South43015450.278
Phase 2East35014400.243 (critical)
Phase 2West31513090.241
Y=0.281+0.243=0.524Y = 0.281 + 0.243 = 0.524

Step 2: Lost time

Lost time per phase = start-up loss 1.5 s + amber 2 s = 3.5 s.

L=(1.5+2.0)+(1.5+2.0)=7.0 sL = (1.5+2.0) + (1.5+2.0) = 7.0\ \text{s}

Step 3: Optimum cycle time (Webster)

C0=1.5L+51−Y=1.5(7.0)+51−0.524=32.6 sC_0 = \frac{1.5L + 5}{1 - Y} = \frac{1.5(7.0) + 5}{1 - 0.524} = 32.6\ \text{s}

Adopt C = 35 s.

Step 4: Green times

Total effective green =C−L=35−7.0=28.0= C - L = 35 - 7.0 = 28.0 s, divided in proportion to yy:

g1=yY(C−L)=0.2810.524(28.0)=15.0 sg_{1} = \frac{y}{Y}(C-L) = \frac{0.281}{0.524}(28.0) = 15.0\ \text{s} g2=yY(C−L)=0.2430.524(28.0)=13.0 sg_{2} = \frac{y}{Y}(C-L) = \frac{0.243}{0.524}(28.0) = 13.0\ \text{s}

Displayed green G=g+G = g + start-up loss (so that ∑G+∑I+R=C\sum G + \sum I + R = C):

PhaseEffective g (s)Start-up loss (s)Green G (s)Amber (s)
Phase 115.01.5172
Phase 213.01.5142

Check: 17 + 2 + 14 + 2 = 35 s.

Phase diagram

|      P1 green 17      |  A2 |    P2 green 14    |  A2 |