- 2079 Jestha · 4 marks
Job layout for 1000 sqm public building
Short answer
Place the 1000 m² building centrally on the 190 m × 125 m plot with a loop road and gates on the front side. Locate office, stores, yards, mixer, water tank and hoist near the building; put labour camp, canteen, toilets, first aid, parking, generator and security on the sides. Keep remaining area for finishing and landscaping.
Prepare a job lay-out plan for constructing 1000 sqm area public building in a rectangular land (190 m × 125 m) with sufficient facilities.
Assumptions: the 1000 m² public building (say 2–3 storeys, plinth about 400 m²) is built in the middle of a 190 m × 125 m plot, the access road runs along one 190 m (front) side, and the RCC frame is built using a mixer and a hoist or small tower crane.
Layout plan (not to scale)
190 m
+--------------------------------------------+
| Labour camp Toilets Canteen First aid |
| |
| Steel yard Carpentry Bar-bending | 125 m
| |
| Sand/agg. +------------+ Cement store |
| stacks | BUILDING | Mixer/batch |
| Brick yard | (1000 m2) | Water tank |
| +------------+ |
| Parking Fire point Generator |
| Site office Security Test lab corner |
+---------[ Main gate ]--[ Material gate ]---+
Access road (190 m side)
Facilities provided
- Gates and roads: separate main gate and material gate; a 4–5 m wide haul road in a loop around the building, one-way if possible.
- Site office near the gate, with space for drawings and meetings, a store for site records, and a small lab corner for cube and slump tests.
- Stores: a closed cement store (raised floor, near the mixer), a general store for tools, fittings and paint, and a steel yard with a covered area.
- Stacking yards: sand, aggregate and bricks on firm ground near the mixer and hoist, with drainage.
- Workshops: carpentry and shuttering yard, bar-bending yard.
- Mixer / batching plant, water tank and curing point near the building, within the crane's reach.
- Labour camp, canteen, toilets and first aid on one side, away from the dust and noise.
- Services: temporary electricity with a generator, a bore or tank water supply, drainage and sewerage.
- Safety and security: boundary fence, fire extinguishers and sand buckets, a watchman, helmets and sign boards.
- Parking for visitors and vehicles, and an assembly point for emergencies.
- Space for future work: the remaining area is kept free for later finishing and landscaping.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Typical job layout of a building project · Construction Management, chapter 6 · asked 4×
- Job layout and site planning factors · Construction Management, chapter 6 · asked 2×
- Value of a 20-year-old building · Construction Management, chapter 13 · asked 2×
- Value of a 10-year-old building · Construction Management, chapter 13 · asked 2×
- Loan value against mortgage of a building · Construction Management, chapter 13
- Capitalized value of 80-year building · Construction Management, chapter 13
- Staircase for public building (5.5 m × 6.5 m) · Building Technology, chapter 5
- Channel earthwork and land area, 50 cm fall · Estimating and Costing, chapter 6 · asked 2×
- Passive solar design and building layout · Building Technology, chapter 1
- Channel earthwork and land area, bed 4 m · Estimating and Costing, chapter 6 · asked 2×