Quotation for a power transformer

Short answer

For a 2x12 MW plant, step-up to 132 kV: specify 16 MVA, 11/132 kV, YNd11, ONAN/ONAF, 10% impedance, with hill transport measures. Indicative total cost for two units with spares and erection is about NPR 10,79,15,000 including VAT.

Make a tentative an example type quotation of a "Power Transformer" for power evacuation purpose from switch yard of a general medium size hydropower project situated in hilly region.

A tentative quotation for a power transformer gives the main technical particulars, scope, price and terms so that the developer can budget and compare offers. Assumed project: a medium hydropower plant of 2 × 12 MW in a hilly region (altitude about 1500 m), evacuating at 132 kV. One step-up transformer per unit.

Rating: S=12/0.85=14.1S = 12/0.85 = 14.1 MVA, so a standard 16 MVA unit is chosen.

Main technical particulars offered

ItemOffered value
Type3-phase, oil-immersed, outdoor, two-winding step-up
Rating16 MVA ONAN / 20 MVA ONAF
Voltage ratio11 / 132 kV, off-circuit taps ±2 × 2.5% on HV
Vector groupYNd11 (HV neutral solidly earthed)
Impedance10% ± IEC tolerance
Frequency50 Hz
Insulation level (HV)BIL 650 kVp, power frequency 275 kV (corrected for altitude)
Losses (guaranteed)No-load ≤ 12 kW; load loss ≤ 85 kW at 75 °C
Temperature riseOil 50 K, winding 55 K (reduced for altitude above 1000 m, IEC 60076-2)
AccessoriesBuchholz relay, PRV, OTI/WTI, MOG, silica gel breather, HV/LV bushings, bushing CTs, radiators, fans, marshalling box
Hill transportShipping weight limited to about 30 t; may ship oil-filled or N2N_2-filled, radiators separate
StandardIEC 60076

Price schedule (indicative)

S.N.DescriptionQtyUnit price (NPR)Amount (NPR)
116/20 MVA, 11/132 kV power transformer as above, with first oil filling24,50,00,0009,00,00,000
2Mandatory spares (bushings, gaskets, Buchholz relay)1 lot–15,00,000
3Transport to site, supervision of erection and commissioning1 lot–40,00,000
Subtotal9,55,00,000
VAT 13%1,24,15,000
Grand total10,79,15,000

Commercial terms

  • Delivery: 7–9 months after LC; FOR site; route survey by supplier.
  • Tests: routine tests (ratio, vector group, losses, impedance, insulation) witnessed by the owner; type test reports (temperature rise, impulse) submitted.
  • Loss capitalisation: bids are compared with the capitalised value of guaranteed losses; a penalty applies for excess losses.
  • Warranty: 24 months after commissioning; payment by LC; validity 120 days.

Prices are only indicative for budgeting; actual prices come from competitive bids.