Quotation for HV breaker of a 48 MW plant

Short answer

Assuming 132 kV evacuation, full load current 247 A gives 1250 A rating. Quote four 145 kV SF6 outdoor live-tank breakers, 31.5 kA, spring-charged, with spares and supervision, total indicative cost NPR 2,61,03,000 including VAT.

Make a tentative an example type quotation of a high voltage side "circuit breaker" for power evacuation purpose at switch yard of a hydropower project that has installed capacity about 48 MW and line length to grid point substation is about 15 km.

A tentative quotation lists the technical data, quantity and price of the breaker so that the developer can budget and compare offers. Assumptions: 48 MW plant with 2 × 24 MW units, evacuation at 132 kV over 15 km by a double-circuit line, so the switchyard has 2 transformer bays and 2 line bays.

Rated current check: IFL=48/0.853×132=247I_{FL} = \dfrac{48/0.85}{\sqrt{3} \times 132} = 247 A, so a standard 1250 A rating is ample.

QUOTATION (example, indicative prices)

To: XYZ Hydropower Ltd., Kathmandu. Ref: 132 kV switchyard circuit breakers. Validity: 90 days.

S.N.DescriptionQtyUnit price (NPR)Amount (NPR)
1145 kV, 3-pole, outdoor SF6 live-tank circuit breaker, 1250 A, 31.5 kA for 3 s, making 80 kA peak, BIL 650 kVp, spring-charged mechanism, O-0.3 s-CO-3 min-CO, single-pole operation for auto-reclose (line bays), 110 V DC control, SF6 density monitor, support structure455,00,0002,20,00,000
2Spares: trip/close coils, gas filling kit, density monitor1 lot–5,00,000
3Supervision of erection and testing at site1 lot–6,00,000
Subtotal2,31,00,000
VAT 13%30,03,000
Grand total2,61,03,000

Terms:

  • Standards: IEC 62271-100; type test reports enclosed.
  • Delivery: CIF Birgunj/site within 6 months of LC; packing for hill transport.
  • Warranty: 24 months from commissioning; payment by LC (10% advance, 80% on delivery, 10% after commissioning).

Prices are only indicative for budgeting; actual prices come from competitive bids.