- 2080 Chaitra · 4 marks
T/F: under-loaded distribution transformer losses
Short answer
FALSE. Transformers have constant core loss whenever energized. At very light loads, copper loss is small but core loss continues, causing percentage energy loss to rise. Maximum efficiency occurs where copper loss equals core loss (typically 40–60% load). Gross underloading wastes energy.
State whether the following statement is TRUE or FALSE and justify your answer with brief explanation: A distribution transformer operating at significantly under-loading conditions is always beneficial from energy loss prospective.
FALSE.
Justification:
A transformer has two kinds of loss:
- No-load (core) loss : constant whenever the transformer is energised, regardless of load.
- Load (copper) loss: , where is the fraction of rated load.
Efficiency is maximum when copper loss equals core loss, i.e. at load fraction
which is typically 40–60% of rating for distribution transformers.
When the transformer is significantly under-loaded:
- Copper loss becomes very small, but the core loss continues for all 8760 hours.
- The energy delivered is small, so the percentage energy loss rises.
Example: 100 kVA unit, W, W, LLF taken as 0.3 for illustration.
| Peak load | Core loss (kWh/yr) | Cu loss (kWh/yr) | Total |
|---|---|---|---|
| 20 kVA | 1752 | 1100 × 0.04 × 0.3 × 8.76 = 116 | 1868 |
| 60 kVA | 1752 | 1100 × 0.36 × 0.3 × 8.76 = 1041 | 2793 |
The 20 kVA case carries one-third of the load but has two-thirds of the losses, so loss per kWh delivered is about twice as high.
Therefore gross under-loading (oversized transformers) wastes energy through core loss, as well as capital. Moderate under-loading near the maximum-efficiency point is beneficial; very light loading is not. This is why transformers should be sized for the realistic design-year demand and why low-loss cores are used where load factor is low.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- T/F: % power loss equals % energy loss · Transmission and Distribution System Design, chapter 6
- T/F: LLF unity for constant power loss · Transmission and Distribution System Design, chapter 6
- Energy loss of 100 kVA transformer in third year · Transmission and Distribution System Design, chapter 7
- T/F: rural design, transformer size first · Transmission and Distribution System Design, chapter 7
- T/F: X/R ratio, transmission vs distribution · Transmission and Distribution System Design, chapter 1
- T/F: lightning overvoltage in distribution system · Transmission and Distribution System Design, chapter 3
- True/false: derivative controllers always used with others · Control Systems, chapter 7 · asked 3×
- True/False: magnetic loading and teeth flux density · Electric Machine Design, chapter 5
- True/false: rotor core loss neglected · Electrical Machine, chapter 5
- True/false: series motor started at no load · Electrical Machine, chapter 4
All Transmission and Distribution System Design chapter 7 questions →