- 2073 Magh · 5 marks
Embankment 1,00,000 m³ excavation
Short answer
Excavate 1,53,333 m³ of soil, with a moist weight of 1.84×10⁶ kN (dry weight 1.6×10⁶ kN).
An embankment of 1,00,000 m³ volume has to be constructed by compacting the soil brought from an excavation site. After compaction, the dry unit weight of the compacted soil (embankment) will be 16 kN/m³. Also, the bulk unit weight and water content of the soil at the excavation site are 12 kN/m³ and 15%, respectively. Find the volume and weight of soil to be excavated from the excavation site. Take specific gravity of soil solid as 2.70.
Given
Embankment: m³, kN/m³. Excavation site: kN/m³, , .
Dry weight needed in the embankment
Dry unit weight at the excavation site
Volume to be excavated
Weight of soil to be excavated (moist)
(check: kN)
The specific gravity is not needed for this answer; it would only be used to find void ratios.
Answer: volume m³; weight kN (dry weight kN).
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Compacted soil 17 kN/m³, OWC 16% · Soil Mechanics, chapter 5 · asked 2×
- Embankment excavation quantity (18 kN/m³) · Soil Mechanics, chapter 2
- Compacted soil 18 kN/m³, porosity and ZAV · Soil Mechanics, chapter 5 · asked 2×
- Compacted soil 18 kN/m³, saturation · Soil Mechanics, chapter 5
- Embankment volume from void ratios · Soil Mechanics, chapter 2
- Compaction test: curve, MDD, OMC, RC · Soil Mechanics, chapter 5 · asked 2×
- EVA; 60 days, 25% work, Rs 12,00,000 · Project Engineering, chapter 4
- Embankment volume, 160 m, rising gradient 1 in 100 · Surveying I, chapter 9
- Flexible design: four-lane, AADT 12,000 · Transportation Engineering II, chapter 2
- EPS and book value; ABC project Rs 6,00,000 · Project Engineering, chapter 6