- 2076 Asoj · 6 marks
Embankment volume, 160 m, rising gradient 1 in 100
Short answer
For level cross-sections, fill heights computed with formation at 1116.95 m rising 1 in 100. Areas using (b+sh)h. Trapezoidal volume 4697.10 m³, prismoidal volume 5720.87 m³, correction -1023.77 m³.
A roadway embankment of formation width of 10 m and side slope 2:1 is to be constructed. The ground level along the centre line is as follows.
| Chainage | 0+000 | 0+040 | 0+080 | 0+120 | 0+160 |
|---|---|---|---|---|---|
| GL (m) | 1115.70 | 1114.30 | 1116.75 | 1115.15 | 1118.45 |
The embankment has a rising gradient of 1 in 100 and the formation level at zero chainage is 114.95 m [?]. Assuming the ground level across the centre line, compute the volume of earth work.
Reading of the given data: the scanned formation level "114.95 m" cannot be right for ground levels near 1115 m (it would put the formation about 1000 m below the ground). Read as 1114.95 m, the formation would switch between cutting and filling at every section, which does not fit an embankment. It is therefore taken here as 1116.95 m at 0+000, which keeps the formation above the ground at every chainage. "Ground level across the centre line" is taken to mean level cross-sections (no transverse slope). Formation width m, side slope (2:1), spacing m.
Step 1: Formation levels and heights of fill
The formation rises at 1 in 100, i.e. m per 40 m: . Height of fill .
| Chainage (m) | GL (m) | FL (m) | h (m) |
|---|---|---|---|
| 0 | 1115.70 | 1116.95 | 1.25 |
| 40 | 1114.30 | 1117.35 | 3.05 |
| 80 | 1116.75 | 1117.75 | 1.00 |
| 120 | 1115.15 | 1118.15 | 3.00 |
| 160 | 1118.45 | 1118.55 | 0.10 |
Step 2: Cross-sectional areas
For a level section of an embankment, the area is a trapezoid:
| Chainage (m) | h (m) | b + s·h (m) | A (m²) |
|---|---|---|---|
| 0 | 1.25 | 12.50 | 15.625 |
| 40 | 3.05 | 16.10 | 49.105 |
| 80 | 1.00 | 12.00 | 12.000 |
| 120 | 3.00 | 16.00 | 48.000 |
| 160 | 0.10 | 10.20 | 1.020 |
Step 3: Trapezoidal formula
Step 4: Prismoidal formula
There are four equal intervals (an even number), so Simpson's rule applies.
Step 5: Prismoidal correction
Answer: Volume of earthwork (filling) = 4697.10 m³ by the trapezoidal formula and 5720.87 m³ by the prismoidal formula (prismoidal correction = -1023.77 m³).
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Cutting volume, 120 m, upward slope 1 in 40 · Surveying I, chapter 9 · asked 8×
- Cut and fill volume, 20 m formation width · Surveying I, chapter 9
- Cutting volume, 60 m, formation level 279.00 · Surveying I, chapter 9 · asked 7×
- Cutting volume, 60 m, formation level 278.00 · Surveying I, chapter 9 · asked 7×
- Earthwork volume, formation 1201.85, 1.65 m depth · Surveying I, chapter 9
- Filling volume, 60 m, formation 1281.49 · Surveying I, chapter 9
- Road earthwork, rising 1 in 200, falling 1 in 120 · Estimating and Costing, chapter 6
- Side-long ground hill road, 0-400 m · Estimating and Costing, chapter 6
- Road earthwork, RD 0-120, gradient 1 in 150 · Estimating and Costing, chapter 6
- Road earthwork, formation level at 150 m · Estimating and Costing, chapter 6 · asked 2×