Real power/frequency control in interconnected system

Short answer

A load increase initially draws kinetic energy, lowering frequency. Primary control uses speed governor droop to share the load change among all units, leaving a steady-state error. Secondary control (AGC) integrates ACE = ΔPtie + BΔf to adjust generation and restore nominal frequency and scheduled tie-line flows.

Explain how real power/frequency control is maintained in a interconnected power system.

In an interconnected system all generators run at one common frequency. Frequency stays constant only while total generation = total load + losses. Real power/frequency control (load-frequency control, LFC) keeps this balance.

What happens on a load change

  1. Inertial response (first seconds): when load rises by ΔPL\Delta P_L, the deficit is supplied from the kinetic energy of all rotors. From the swing equation 2Hωsd2δdt2=Pm−Pe\frac{2H}{\omega_s}\frac{d^2\delta}{dt^2} = P_m - P_e, they slow down and frequency falls.
  2. Primary control (governor): each speed governor senses Δf\Delta f and opens the turbine valve/gate. With speed regulation (droop) RR:
ΔPm,i=−ΔfRi,Δfss=−ΔPL∑i1Ri+D\Delta P_{m,i} = -\frac{\Delta f}{R_i},\qquad \Delta f_{ss} = \frac{-\Delta P_L}{\sum_i \dfrac{1}{R_i} + D}

The load change is shared by all units of all areas, in inverse proportion to their droop. A steady-state frequency error remains, and tie-line flows change from schedule. 3. Secondary control (AGC): each area computes its Area Control Error

ACEi=ΔPtie,i+Bi ΔfACE_i = \Delta P_{tie,i} + B_i\,\Delta f

An integral controller changes the speed-changer set points until ACEi=0ACE_i = 0. Frequency returns to nominal and each area again supplies its own load, with tie flows back at schedule. 4. Tertiary control: economic dispatch sets the new outputs at minimum cost.

 dPL -> [Power system] -> df
           ^               |
           |  dPm          v
      [Turbine] <- [Governor 1/R] <- df
           ^
     speed changer <- integral(ACE)

Example: in a two-area system, if area 1 load increases, at first both areas raise generation and power flows from area 2 to area 1 over the tie-line; AGC in area 1 then raises its own generation so the tie-line flow returns to schedule.