Skip to main content

Cross drainage: Q 50, HFD 400, d 1.55 m

Short answer

Drainage waterway: 12 spans of 8 m, clear waterway 96 m. Canal waterway: flumed trough 18 m wide, 1.55 m deep. Inlet transition 2:1 splay 16.6 m; outlet 3:1 splay 25.0 m. Bed levels: 300.000, 299.853, 299.799, 299.855 m; head loss 0.145 m.

Design the following components of a suitable C/D work for the following data: Discharge of canal = 50 m³/s, Bed width of canal = 30 m, Depth of water in canal = 1.55 m, Bed level of canal = 300.0 m, High flood discharge of drain = 400 m³/s, High flood level of drainage = 300.50 m, Bed level of drainage = 298.8 m, General ground level = 300.0 m. i) Design of drainage water-way ii) Design of canal water way iii) Design of transition iv) Design of bed levels.

The canal (QQ = 50 m³/s) crosses a drainage of QQ = 400 m³/s. Design is done in four steps: type of work, drainage waterway, canal waterway (flumed trough) and bed/water levels of the trough.

Assumptions: Side slope not given, taken 1.5:1; Lacey's ff = 1; trough nn = 0.015.

1. Type of structure

HFL of the drainage (300.50 m) is above the canal bed (300.00 m) by 0.50 m, so the trough cannot be kept above HFL without a very high, costly structure. The drainage is passed under the trough through barrels flowing under pressure (siphonic action). A siphon aqueduct is suitable. Drainage depth at HFL = 300.50 − 298.80 = 1.70 m.

2. Drainage waterway

Lacey's regime perimeter (for a natural stream):

P=4.75Q=4.75400=95.0 mP = 4.75\sqrt{Q} = 4.75\sqrt{400} = 95.0\ \text{m}

Provide 12 spans of 8 m with piers 1.2 m thick: clear waterway = 12 × 8 = 96 m (> 95.0 m). Overall length = 96 + 11 × 1.2 = 109.2 m.

Check: mean velocity = Q/(L·d) = 400/(96 × 1.70) = 2.45 m/s. Lacey's regime depth R=0.47(Q/f)1/3R = 0.47(Q/f)^{1/3} = 3.46 m (with ff = 1); foundations of piers and abutments are taken about 1.5R = 5.2 m below HFL, with cut-offs and aprons for scour.

3. Canal waterway (flumed rectangular trough)

Normal canal: area A1=(B+zD)DA_1=(B+zD)D = (30 + 1.5 × 1.55) × 1.55 = 50.10 m², V1V_1 = 50/50.10 = 0.998 m/s, hv1=V12/2gh_{v1}=V_1^2/2g = 0.0508 m. Top width T=B+2zDT=B+2zD = 34.65 m.

To save cost, the canal is flumed to a rectangular trough of width BtB_t = 18 m, with the same full supply depth 1.55 m (the trough is as long as the drainage waterway, 109.2 m).

  • Trough area = 18 × 1.55 = 27.90 m²; VtV_t = 50/27.90 = 1.792 m/s (acceptable, < 2.5 m/s); hvth_{vt} = 0.1637 m
  • Froude number = 0.46 < 1, flow is subcritical, so there is no hydraulic jump.
  • Hydraulic radius R=A/PR=A/P = 27.90/21.10 = 1.322 m; friction slope S=(nV/R2/3)2S=(nV/R^{2/3})^2 = 0.000498 (Manning's n = 0.015); friction loss in trough hf=S Lh_f=S\,L = 0.000498 × 109.2 = 0.054 m

4. Transitions and levels

  FSL ---.                            .--- FSL
         '--.______________________.--'
  bed ---.                            .--- bed
         '--.______________________.--'
  normal  inlet     flumed trough     outlet  normal
  canal   (2:1)                      (3:1)   canal

Wing-wall (straight) transitions: inlet splay 2:1 (contraction) and outlet splay 3:1 (expansion), measured on each side:

  • Inlet length = 2 × (T − B_t)/2 = 34.65 − 18 = 16.6 m
  • Outlet length = 3 × (T − B_t)/2 = 25.0 m

Bernoulli's equation between sections (loss in contraction = 0.3 Δh_v, in expansion = 0.5 Δh_v; Δh_v = difference of velocity heads):

W2=W1+hv1−hvt−0.3(hvt−hv1)W3=W2−hfW4=W3+hvt−hv1−0.5(hvt−hv1)\begin{aligned} W_2 &= W_1 + h_{v1} - h_{vt} - 0.3(h_{vt}-h_{v1}) \\ W_3 &= W_2 - h_f \\ W_4 &= W_3 + h_{vt} - h_{v1} - 0.5(h_{vt}-h_{v1}) \end{aligned}

W1W_1 = 301.550 m, so W2W_2 = 301.403 m, W3W_3 = 301.349 m, W4W_4 = 301.405 m. Trough bed = water level − 1.55 m.

SectionLocationBed level (m)FSL (m)
1Normal canal, start of inlet transition300.000301.550
2End of inlet transition = start of trough299.853301.403
3End of trough = start of outlet transition299.799301.349
4End of outlet transition = normal canal299.855301.405

Total loss of head = 301.550 − 301.405 = 0.145 m, so the canal bed downstream of the work is 0.145 m lower than upstream.

Check: with trough slab 0.6 m thick, soffit of the barrels = 299.20 m, i.e. 0.40 m above the drainage bed; HFL stands 1.30 m above the soffit, which gives the siphonic head. Since the clear height is less than 1.5 m, the drainage bed is depressed under the barrels to RL 297.70 m (1.5 m clear height) with a 1 in 4 slope at both ends.

Answer: drainage waterway 96 m clear (12 × 8 m, overall 109.2 m); canal flumed to 18 m wide trough; bed/FSL at the four sections = 300.00/301.55, 299.85/301.40, 299.80/301.35, 299.86/301.41 m.

✓ Answer checked by Claude Opus 5.5 (high effort)

All Irrigation and Drainage Engineering chapter 8 questions →