Launching apron thickness before launching

Short answer

Equate stone volume before and after launching: laid width 1.8D, launched slope length √10D, T×1.8D = 1.5t×√10D, so T = 2.64t. The apron is laid about 2.6 times the pitching thickness.

The launching apron of a guide bank is laid in a width equal to 1.8 times the depth of scour below original bed. If a scour slope of 3:1 is to be maintained with thickness 1.5 t, find the thickness of apron before it gets launched. Draw neat sketch of designed structure.

A launching apron is laid flat at the toe of the pitching. When the bed scours, the stones slide down the scour slope and cover it. The thickness before launching follows from equality of the stone volume per metre run before and after launching.

Data

  • Scour depth below original bed =D= D (unknown, cancels out).
  • Laid width of apron =1.8D= 1.8D; scour slope 3H:1V3H:1V; launched thickness =1.5t= 1.5t (tt = thickness of pitching).

Calculation

Length of the scour slope: D2+(3D)2=10 D=3.162D\sqrt{D^2 + (3D)^2} = \sqrt{10}\,D = 3.162D.

Volume per metre after launching: V=1.5t×3.162D=4.743 tDV = 1.5t\times3.162D = 4.743\,tD.

Volume per metre before launching: V=T×1.8DV = T\times1.8D, where TT is the thickness as laid.

T×1.8D=1.5t×10 DT=1.5101.8 t=2.635 t\begin{aligned} T\times1.8D &= 1.5t\times\sqrt{10}\,D \\ T &= \frac{1.5\sqrt{10}}{1.8}\,t = 2.635\,t \end{aligned}

Answer: thickness of apron before launching T≈2.64 tT \approx 2.64\,t (that is, about 2.6 times the pitching thickness).

Sketch

 Before launching            After launching (3H:1V)
  pitching                     pitching
 ___\____ T                   ___\
      |<--1.8D-->|                 \  1.5t thick
 bed ____apron___| river bed        \ scour slope
                                     \__ depth D

For example, if t=1.0t = 1.0 m the laid thickness is 2.64 m.