Skip to main content

Silt excluder design, Q 200 cumec

Short answer

Assume tunnel discharge 40 m³/s (20% of 200). Height = (227.35−225.25)−0.30 = 1.80 m. Area = 40/2.5 = 16 m², width = 8.89 m. Provide 3 tunnels each 3.0 m wide with two 0.6 m piers to fit 10.2 m bay. Velocity = 2.47 m/s. Result: 3 tunnels 3.0 m×1.80 m, piers 0.6 m, carrying 40 m³/s at 2.47 m/s.

Design a silt excluder for the diversion head works having following data: Full supply discharge of canal = 200 m³/sec; Crest level of undersluices = 225.25 m; Crest level of head regulator = 227.35 m; Bay width of undersluices = 10.2 m.

Given and assumptions

Canal discharge Q=200Q = 200 m³/s; undersluice crest level (tunnel floor) =225.25= 225.25 m; head regulator crest level =227.35= 227.35 m (tunnel roof level); bay width of the undersluices =10.2= 10.2 m.

Assumed: discharge through the tunnels = 20% of the canal discharge; roof slab thickness 0.3 m; tunnel velocity about 2.5 m/s (non-silting); pier thickness 0.6 m.

Design

  1. Discharge in tunnels
Qt=0.20×200=40 m3/sQ_t = 0.20\times 200 = 40\ \text{m}^3/\text{s}
  1. Height of tunnels

Difference of crest levels =227.35−225.25=2.10= 227.35 - 225.25 = 2.10 m. Subtracting the roof slab of 0.300.30 m:

h=2.10−0.30=1.80 mh = 2.10 - 0.30 = 1.80\ \text{m}
  1. Area of tunnels
A=QtV=402.5=16.0 m2A = \frac{Q_t}{V} = \frac{40}{2.5} = 16.0\ \text{m}^2
  1. Total width of tunnels
W=Ah=16.01.80=8.89 mW = \frac{A}{h} = \frac{16.0}{1.80} = 8.89\ \text{m}
  1. Number of tunnels. Provide 3 tunnels of 3.0 m each and 2 piers of 0.6 m:
Total width=3×3.0+2×0.6=10.2 m\text{Total width} = 3\times 3.0 + 2\times 0.6 = 10.2\ \text{m}

which fits exactly in the bay width of 10.2 m. Area provided =3×3.0×1.80=16.20= 3\times 3.0\times 1.80 = 16.20 m².

  1. Velocity check
V=4016.20=2.47 m/sV = \frac{40}{16.20} = 2.47\ \text{m/s}

This is very slightly below 2.5 m/s (about 1% less), which is practically acceptable; it lies within the usual tunnel velocity range of 2-3 m/s, so the silt will be carried through the tunnels.

Section

 regulator crest 227.35 -----------------------
        roof slab (0.30)  ===================
        tunnel height 1.80 |  |  |  |  |  |
 undersluice crest 225.25 -----------------------
 3 tunnels x 3.0 m + 2 piers x 0.6 m = 10.2 m

Answer: 3 tunnels, each 3.0 m wide and 1.80 m high (roof 227.35 m, floor 225.25 m), piers 0.6 m, carrying 40 m³/s at about 2.47 m/s.

✓ Answer checked by Claude Opus 5.5 (high effort)

All Irrigation and Drainage Engineering chapter 5 questions →