Vertical drop design, Q 5.1 m3/s

Short answer

Crest level is 255.15 m with a length of 2.5 m. The drop wall has a top width of 0.5 m and bottom width of 1.52 m. The impervious floor total length is 8.10 m with a thickness of 0.50 m near the wall.

Design a vertical type drop structure for the following data: Discharge = 5.1 m³/sec; Bed level U/S = 255.15 m, D/S = 254.45 m; Normal flow depth U/S, D/S = 0.95 m; Bed width of canal U/S, D/S = 2.5 m; Side slope of canal = 1:1. Take the top width of crest wall as 0.5 m for initial assumption. Assume other suitable data if necessary.

Given data and assumptions

  • Q=5.1Q = 5.1 m³/s, bed width B=2.5B = 2.5 m, side slope 1:1, u/s bed =255.15= 255.15 m, d/s bed =254.45= 254.45 m.
  • U/s FSL == bed ++ normal depth =255.15+0.95=256.10= 255.15 + 0.95 = 256.10 m; d/s FSL =254.45+0.95=255.40= 254.45 + 0.95 = 255.40 m. Full supply depth Du=Dd=0.950D_u = D_d = 0.950 m; drop in water level HL=0.700H_L = 0.700 m.
  • Assumed (not given): Bligh's coefficient C=6C = 6 (sandy loam soil), specific gravity of masonry G=2.24G = 2.24, and Cd=0.415C_d = 0.415 for a rectangular crest.

1. Upstream flow conditions

A=(B+mDu)Du=(2.5+1×0.950)(0.950)=3.278 m2v=Q/A=1.556 m/s,ha=v22g=0.123 m\begin{aligned} A &= (B + mD_u)D_u = (2.5 + 1\times0.950)(0.950) = 3.278\ \text{m}^2 \\ v &= Q/A = 1.556\ \text{m/s}, \qquad h_a = \frac{v^2}{2g} = 0.123\ \text{m} \end{aligned}

2. Crest length, head and crest level

Discharge over a rectangular crest: Q=Cd2g L H3/2Q = C_d\sqrt{2g}\,L\,H^{3/2} with Cd2g=1.838C_d\sqrt{2g} = 1.838, where HH is the total head over the crest (including hah_a). Take crest length equal to the bed width, L=BL = B:

H=(Q1.838 L)2/3=(5.11.838×2.5)2/3=1.072 mH = \left(\frac{Q}{1.838\,L}\right)^{2/3} = \left(\frac{5.1}{1.838\times2.5}\right)^{2/3} = 1.072\ \text{m} Crest level=FSLu+ha−H=256.100+0.123−1.072=255.15 m\text{Crest level} = FSL_u + h_a - H = 256.100 + 0.123 - 1.072 = 255.15\ \text{m}

Height of crest above d/s bed dc=255.15−254.45=0.70d_c = 255.15 - 254.45 = 0.70 m.

3. Cistern (energy dissipation)

Discharge per metre length of crest q=Q/L=2.040q = Q/L = 2.040 m²/s. Energy available above the d/s bed E1=FSLu+ha−d/s bed=1.773E_1 = FSL_u + h_a - \text{d/s bed} = 1.773 m. For a cistern of depth XX below the d/s bed, the jump must form with the conjugate depth y2y_2 equal to the tail water over the cistern, y2=Dd+Xy_2 = D_d + X. Solving with E1+X=y1+q2/(2gy12)E_1 + X = y_1 + q^2/(2gy_1^2) and y2=y12(1+8F12−1)y_2 = \frac{y_1}{2}(\sqrt{1+8F_1^2} - 1):

  • Required X=0.494X = 0.494 m. Provide X=0.50X = 0.50 m (cistern floor level =253.95= 253.95 m).
  • With this XX: y1=0.330y_1 = 0.330 m, F1=3.43F_1 = 3.43, y2=1.446y_2 = 1.446 m.

Length of cistern (hydraulic jump length) Lc=5(y2−y1)=5(1.446−0.330)=5.58L_c = 5(y_2 - y_1) = 5(1.446 - 0.330) = 5.58 m.

4. Crest (drop) wall

Top width (assumed) T=0.50T = 0.50 m; check 0.55dc=0.550.70=0.460.55\sqrt{d_c} = 0.55\sqrt{0.70} = 0.46 m <0.50< 0.50 m, so it is adequate. Height of wall from cistern floor to crest Hw=255.15−253.95=1.20H_w = 255.15 - 253.95 = 1.20 m. Bottom width for a gravity masonry wall:

Bw=Hw+HG=1.20+1.072.24=1.52 mB_w = \frac{H_w + H}{\sqrt{G}} = \frac{1.20 + 1.07}{\sqrt{2.24}} = 1.52\ \text{m}

Adopt bottom width Bw=1.52B_w = 1.52 m (not less than the top width), with the d/s face vertical or slightly battered.

5. Length of impervious floor (Bligh's theory)

Total creep length required L=C HL=6×0.700=4.20L = C\,H_L = 6\times0.700 = 4.20 m. Cut-offs: u/s d1=0.6d_1 = 0.6 m, d/s d2=0.9d_2 = 0.9 m. Downstream floor length (Bligh) with qq in m²/s:

Ld=2.21 CHLq/75=2.21×60.7002.040/75=4.51 mL_d = 2.21\,C\sqrt{H_L\sqrt{q/75}} = 2.21\times6\sqrt{0.700\sqrt{2.040/75}} = 4.51\ \text{m}

The d/s floor (measured from the toe of the wall) must also contain the cistern, so adopt Ld=5.58L_d = 5.58 m. Creep already provided by cut-offs and wall =2(d1+d2)+Bw=4.52= 2(d_1 + d_2) + B_w = 4.52 m, so the u/s floor needed is

bu=L−[2(d1+d2)+Bw+Ld]=−5.90 mb_u = L - [2(d_1+d_2) + B_w + L_d] = -5.90\ \text{m}

Bligh's creep is already satisfied, so a nominal u/s floor of 1.0 m is provided. Actual creep =11.10= 11.10 m ≥4.20\ge 4.20 m, safe. Total floor length =bu+Bw+Ld=8.10= b_u + B_w + L_d = 8.10 m.

6. Thickness of the floor

Pressure head at the toe of the wall: creep to that point =3.72= 3.72 m, so residual head h1=HL Lact−3.72Lact=0.465h_1 = H_L\,\dfrac{L_{act} - 3.72}{L_{act}} = 0.465 m. At the end of the cistern the creep is 9.30 m and h2=0.114h_2 = 0.114 m.

t1=43h1G−1=43×0.4651.24=0.50 mt_1 = \frac{4}{3}\frac{h_1}{G-1} = \frac{4}{3}\times\frac{0.465}{1.24} = 0.50\ \text{m}

Adopt floor thickness 0.50 m under the cistern near the wall, tapering to 0.30 m at the end of the floor (minimum 0.30 m).

Summary

ComponentValue
Crest level255.15 m
Crest length / head HH2.50 m / 1.07 m
Crest wall top / bottom width0.50 m / 1.52 m
Cistern depth / length0.50 m / 5.58 m
Floor: u/s 1.0 m, d/s 5.58 m, cut-offs 0.6 / 0.9 mtotal creep 11.10 m
Floor thickness0.50 m (taper to 0.30 m)

Answer: crest level 255.15 m, crest length 2.50 m, crest wall 0.50 m top and 1.52 m bottom width, cistern depth 0.50 m and length 5.58 m, floor length 8.10 m, floor thickness 0.50 m.

Sketch:

 FSL u/s ~~~~~~~~~~~|
                    |  crest
 u/s bed ___________|__          FSL d/s ~~~~
        |  u/s floor |  \  drop        ~~~~~
     d1 |            |   \_____cistern________ d/s bed
        |            |<-Lc->|   d/s floor   | d2
                     |____ floor thickness __|