Circular combined sewer, 60 ha

Short answer

Total flow Q=2.535 m³/s. With n=0.013, choosing full-flow velocity 3.0 m/s gives area 0.845 m², D=1.037 m, adopted 1.05 m; actual v=2.93 m/s. Slope from Manning's is 0.00862 (1 in 116). Dry-weather velocity 1.58 m/s ensures self-cleansing.

Design a circular section of combined sewer from the following data: Area to be served = 60 ha Population = 65,000 Maximum permissible velocity = 3.2 m/sec Time of entry = 5 minutes Time of flow = 18 minutes Rate of water supply = 235 lpcd Overall runoff coefficient = 0.55 Assume suitably any other data required.

Part 1: Dry weather flow (sewage) [2 marks]

Assume 80% of 235 lpcd becomes sewage and the peak factor is 3.

Qsew=65000×235×0.8×386400×1000=0.4243 m3/sQ_{sew}=\frac{65000\times235\times0.8\times3}{86400\times1000}=0.4243\ \text{m}^3/\text{s}

Part 2: Design of the combined sewer [6 marks]

Storm water. tc=te+tf=5+18=23t_c=t_e+t_f=5+18=23 min. With the assumed formula i=760t+10i=\dfrac{760}{t+10} mm/hr:

i=76023+10=23.03 mm/hrQstorm=0.55×23.03×60360=2.111 m3/sQ=Qsew+Qstorm=2.535 m3/s\begin{aligned} i&=\frac{760}{23+10}=23.03\ \text{mm/hr}\\ Q_{storm}&=\frac{0.55\times23.03\times60}{360}=2.111\ \text{m}^3/\text{s}\\ Q&=Q_{sew}+Q_{storm}=2.535\ \text{m}^3/\text{s} \end{aligned}

Size. The sewer is designed to run full at peak flow. Take a design velocity of 3.0 m/s (below the maximum permissible 3.2 m/s):

A=Qv=2.5353.0=0.845 m2,D=4Aπ=1.037 mA=\frac{Q}{v}=\frac{2.535}{3.0}=0.845\ \text{m}^2,\qquad D=\sqrt{\frac{4A}{\pi}}=1.037\ \text{m}

Adopt D=1.05D=1.05 m. Then v=Qπ4D2=2.93v=\dfrac{Q}{\frac{\pi}{4}D^2}=2.93 m/s (less than 3.2 m/s).

Slope. From Manning's formula with R=D/4=0.263R=D/4=0.263 m, n=0.013n=0.013:

S=(v nR2/3)2=(2.93×0.0130.2632/3)2=0.00862≈1116S=\left(\frac{v\,n}{R^{2/3}}\right)^2=\left(\frac{2.93\times0.013}{0.263^{2/3}}\right)^2=0.00862\approx\frac{1}{116}

Check at average dry weather flow =Qsew/3=0.1414=Q_{sew}/3=0.1414 m³/s: Q/Qf=0.0558Q/Q_f=0.0558, d/D=0.160d/D=0.160, v=1.58v=1.58 m/s. This is greater than 0.6 m/s, so the self-cleansing condition is satisfied.

Answer: Circular combined sewer, D = 1.05 m, slope about 1 in 116, carrying 2.535 m³/s at 2.93 m/s (running full).