CVTs are needed at EHV levels (≥66 kV) because they are cheaper and lighter than electromagnetic VTs, and the same capacitor stack serves as a coupling capacitor for power line carrier communication. They step down voltage accurately via a tuned reactor, though transient response is poorer.
Explain the need of capacitive voltage transformer in power system.
A capacitive (capacitor) voltage transformer (CVT) steps down extra-high voltage using a capacitor divider followed by a small intermediate electromagnetic VT and tuning reactor.
Need of CVT in power system
- Economy at high voltage: an electromagnetic VT for 132 kV and above needs very heavy insulation, so it becomes large and costly. A capacitor stack handles the high voltage cheaply; only the small IVT works at 10–20 kV. The higher the voltage, the larger the saving.
- Voltage signal for protection and metering: distance relays, directional relays, synchronising, voltmeters and energy meters require a voltage proportional to line voltage (110/√3 V).
- Power line carrier communication (PLCC): the same capacitor stack acts as the coupling capacitor for carrier signals (30–500 kHz) used for teleprotection, telephone and SCADA. One equipment serves two purposes.
- Smaller size and weight: easier transport and installation in EHV switchyards.
- Reduced risk of ferro-resonance with breaker grading capacitors compared with some inductive VTs (with suppression circuit).
- Surge protection: the capacitance helps to slope steep wave fronts.
Working principle (brief)
V_tap = V_line × C1/(C1 + C2)
Tuning: ωL = 1 / [ω(C1 + C2)]
The tuning reactor compensates the capacitive source impedance so that the output is nearly independent of burden.
Limitations
- Poorer transient response: after a fault, the energy stored in capacitors and reactor causes transients that may affect high-speed distance relays.
- Accuracy is affected by frequency and temperature.
Therefore CVTs are standard for line voltage measurement at 66 kV and above.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Construction of capacitor voltage transformer · Switchgear and Protection, chapter 2
- Differential protection of power transformer · Switchgear and Protection, chapter 7
- Voltage-monitored overcurrent relay timing · Switchgear and Protection, chapter 7
- Need of instrument transformers; CT errors · Switchgear and Protection, chapter 2
- Restriking voltage numerical (11 kV, 10 mH) · Switchgear and Protection, chapter 6 · asked 2×
- Specifying breaker on 132/66 kV transformer · Switchgear and Protection, chapter 6
- Transformer at resistive, inductive, capacitive loads · Electrical Machines, chapter 2
- Why terminal voltage exceeds emf on capacitive load · Electric Machines II, chapter 1 · asked 3×
- Load characteristics and capacitive load voltage rise · Electric Machines II, chapter 1 · asked 3×
- Typical power system with voltage levels · Power System Analysis I, chapter 1