- 2070 Magh · 8 marks
Voltage-monitored overcurrent relay timing
Short answer
For a fault just beyond R2, fault current 0.5405 pu reduces terminal voltage to 0.054 pu, activating the voltage monitor. R2 sees 354.6 A: PSM 3.55, time 1.64 s. R1, with plug setting reduced to 40%, has PSM 1.33 and time 2.45 s; it backs up R2.
Figure shows a portion of power system in a single line diagram. Find out the time of operation of relays R1 and R2 for a fault immediately after relaying point R2. Relay R1 is voltage monitored over current relay, the plug setting (PS) of which reduces to 40% of the set value if voltage collapses below 70% of rated voltage. (Assume suitable data if necessary.) [Figure: Generator (Xs = 175%, Xd = 30%, 11 kV, 120 MW, 0.8 pf) with relay R1 (PS = 100%, TDS = 0.1) at its terminals, feeding a step-up transformer (X = 10%, 11/132 kV, 150 MVA) through a breaker to a 132 kV bus. Three outgoing feeders leave the bus through breakers; on one of them relay R2 with CT 200/1 (PS = 50%, TDS = 0.3) and a fault just beyond R2.]
| PSM | 2 | 3 | 5 | 10 | 15 | 20 |
|---|---|---|---|---|---|---|
| Time (sec) | 10 | 6 | 4.1 | 3 | 2.5 | 2.2 |
A voltage-monitored (voltage-controlled) overcurrent relay is used on generators because the sustained fault current of a generator (limited by synchronous reactance) can be less than full-load current, so a plain overcurrent relay would never operate. When the terminal voltage collapses during a fault, its plug setting is reduced so that it can pick up.
Assumptions
- Base 150 MVA (generator 120 MW / 0.8 = 150 MVA); prefault voltage 1.0 pu; three-phase fault just beyond R2; only this generator feeds the fault.
- Relay times are of the order of seconds, so the sustained current with X_s = 175% is used (AVR action neglected).
- R1 CT ratio 8000/1 A (generator rated current 7873 A); R2 CT 200/1 A as given; relay rated current 1 A.
- Table interpolated linearly; for PSM below 2 the IEC normal inverse curve t = 0.14/(PSM^0.02 − 1), which matches the table (gives 10.0 s at PSM 2 and 2.97 s at PSM 10), is used.
Fault current
X_total = X_s + X_T = 1.75 + 0.10 = 1.85 pu
I_f = 1 / 1.85 = 0.5405 pu
I_base(11 kV) = 150×10⁶/(√3×11×10³) = 7872.96 A
I_base(132 kV) = 150×10⁶/(√3×132×10³) = 656.08 A
I_f at 11 kV = 0.5405 × 7872.96 = 4255.7 A
I_f at 132 kV = 0.5405 × 656.08 = 354.6 A
Generator terminal voltage = I_f × X_T = 0.5405 × 0.10
= 0.054 pu (< 0.7 pu)
Relay R2 (feeder)
Relay current = 354.6 / 200 = 1.773 A
Pick-up = 50% × 1 = 0.5 A
PSM = 1.773 / 0.5 = 3.546
t (TDS 1) = 6 − (3.546 − 3)/(5 − 3) × (6 − 4.1) = 5.481 s
t_R2 = 0.3 × 5.481 = 1.644 s
Relay R1 (generator, voltage monitored)
Relay current = 4255.7 / 8000 = 0.532 A
At PS 100%: PSM = 0.532/1 = 0.53 < 1
→ would never operate
Voltage 0.054 pu < 0.7 pu
→ PS reduced to 40% of 100% = 40%
Pick-up = 0.4 A
PSM = 0.532 / 0.4 = 1.33
t (TDS 1) = 0.14 / (1.33^0.02 − 1) = 24.48 s
t_R1 = 0.1 × 24.48 = 2.45 s
Result
| Relay | Current | PS | PSM | TDS | Time |
|---|---|---|---|---|---|
| R2 | 354.6 A (132 kV) | 50% | 3.55 | 0.3 | 1.64 s |
| R1 | 4255.7 A (11 kV) | 100% → 40% | 1.33 | 0.1 | 2.45 s |
Answer: R2 operates in about 1.64 s and R1 in about 2.45 s, so R1 correctly backs up R2 with about 0.8 s margin. Without voltage monitoring, R1 (PSM 0.53) would not operate at all. (Times depend on the assumed R1 CT ratio.)
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- IDMT grading: R1, R2 with 1000/5 CTs · Switchgear and Protection, chapter 7 · asked 2×
- Directional static overcurrent relay · Switchgear and Protection, chapter 8 · asked 2×
- Relay 1 time and relay 2 TMS (3000 A) · Switchgear and Protection, chapter 7
- Minimum TMS of relay A (16000 A fault) · Switchgear and Protection, chapter 7
- Operating time of two relays (250/1, 3000 A) · Switchgear and Protection, chapter 7
- Operating time of two relays (300/1, 6000 A) · Switchgear and Protection, chapter 7
- Show i1 = i2 = -V/(R1+R2+R3) at t=0+ · Electrical Circuit Theory, chapter 2
- Timing diagram of STA, program time · Microprocessor, chapter 2
- 8255 mode 2 operation with timing diagram · Instrumentation II, chapter 2
- Voltage divider bias, DC load line, Q point (20 V) · Basic Electronics Engineering, chapter 3 · asked 2×