Quantity of a semi-circular arch
Short answer
For a semicircular arch, rise equals half span; intrados radius r = span/2 and extrados radius R = r + t. Area is pi/2(R^2 - r^2), volume equals area times wall thickness. With span 2 m, t = 0.30 m and b = 0.23 m, arch masonry is 0.249 m3.
Explain with neat sketches how to work out the quantity of a semi-circular arch (span, thickness and rise of arch given).
A semicircular arch has a rise equal to half the span. The brickwork quantity of the arch is the volume of the arch ring (the area between the intrados and the extrados) multiplied by the wall thickness.
extrados R = r + t
.-----------.
.' .---------. '.
/ / intrados \ \
| | r | |
|__|____________|__|
<---- span --->
S = 2r
Method
- Span , so the radius of the intrados is and the rise equals .
- Radius of the extrados: , where is the thickness (depth) of the arch ring.
- Area of the arch ring (half annulus):
which is the same as mean radius , i.e. . 4. Quantity of arch masonry: , where is the thickness of the wall (the width of the arch along the wall). 5. Deductions from the wall: when the wall masonry is measured gross, deduct from it the opening (the rectangle height up to the springing line, plus the semicircle above it) and also the arch ring volume , because the arch masonry is measured separately at its own rate. The centering for the arch is measured as a separate item.
Worked example (assumed values)
Span 2.0 m ( m), arch thickness m ( m), wall thickness m.
Opening to be deducted from the wall (semicircle above the springing line): m³.
Answer: Arch ring masonry = 0.249 m³ (for the assumed dimensions).
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- RCC slab culvert 1.5 m span: four items · Estimating and Costing, chapter 6
- Work breakdown for frame structure quantities · Estimating and Costing, chapter 2
- Quantity method for load bearing brick building · Estimating and Costing, chapter 2
- Short notes: overhead charge, task work · Estimating and Costing, chapter 4
- Well foundation: excavation, sinking, brick, PCC curb · Estimating and Costing, chapter 6 · asked 2×
- Well foundation: sinking, brick, sand filling, PCC · Estimating and Costing, chapter 6 · asked 2×
- Circular arch ILDs at 3 m, then internal forces · Theory of Structures I, chapter 6 · asked 2×
- Circular arch: BM, shear, thrust at D · Theory of Structures I, chapter 6 · asked 2×
- Circular arch 100 m: rolling UDL 25 m, 15 m section · Theory of Structures I, chapter 6 · asked 2×
- Circular arch: two rolling loads 20 kN and 30 kN · Theory of Structures I, chapter 6 · asked 2×