Hydraulic design of surge tank and pressure tunnel

Short answer

Surge tank design considers location near powerhouse, type (simple, restricted, differential), cross-section larger than Thoma area, maximum upsurge/downsurge limits, oscillation period, and connection with overflow/air vents. Pressurized tunnel design includes economic diameter with velocity 2.5-4 m/s, friction and local losses, internal pressure including water hammer, adequate rock cover to prevent rupture, HGL above crown, concrete/steel lining, and grouting.

Briefly discuss the hydraulic design considerations of the surge tank and pressurised hydraulic tunnel.

Hydraulic design considerations of the surge tank

  • Location: as close to the powerhouse as possible, on stable ground at a level high enough that the maximum surge level stays below the tank top, and the minimum level stays above the tunnel crown.
  • Type: simple, restricted orifice, differential (Johnson), or with an upper/lower chamber, chosen by the head, topography and the required reduction of the surge.
  • Size: the cross-section must be larger than the Thoma area for stability under small load changes:
As≥Ath=L At2g α (H0−hf)A_s\ge A_{th}=\frac{L\,A_t}{2g\,\alpha\,(H_0-h_f)}
  • Surge levels: maximum upsurge on full load rejection must not overflow, and minimum downsurge on full-load demand must not expose the tunnel crown (air entry) or the tank bottom; the oscillation period T=2πLAs/(gAt)T=2\pi\sqrt{LA_s/(gA_t)} should be checked with the governor.
  • Connection: the area of the connecting orifice and the shaft should be sized to give small head loss, but enough damping.
  • Provide an overflow, air vents, and access.

Hydraulic design considerations of a pressurised tunnel

  • Diameter and velocity: from the economic diameter; velocity usually 2.5-4 m/s.
  • Friction and other losses: Manning/Darcy, with nn of lining; plus entry, bend and transition losses.
  • Internal pressure: the maximum internal pressure includes the static head and the surge/water-hammer rise.
  • Minimum rock cover: the cover should resist the internal pressure (about Crm≥hsγwFγrcos⁡βC_{rm}\ge\dfrac{h_s\gamma_w F}{\gamma_r\cos\beta}); otherwise the section is steel-lined.
  • Hydraulic grade line should stay above the crown at all times, in the transient too, so as to avoid vacuum/negative pressure.
  • Lining and grouting: concrete lining for smoothness, steel lining where the rock is weak or the cover is low; contact and consolidation grouting; drainage.
  • Protection: air vents and an emergency gate at the intake, and a surge tank at the downstream end to reduce the water hammer in the tunnel.