EVA; 100 precast windows in 20 days

Short answer

PV=12.50, EV=10.00, AC=9.00 lakh; SV=-2.50, CV=1.00, SPI=0.800, CPI=1.111, so behind schedule and under budget. EAC=22.50 lakh, ETC=13.50 lakh, forecast duration 25 days.

A construction company is planned to fix 100 units of precast window in 20 days with a budget of 25 lakhs. The progress status was reviewed on 10 days from the date of start of fixing and only 40 units were fixed with the expenses of 9 lakhs. Find out all the parameters of earned value analysis and comment on its performance.

All money values are in Rs lakh.

Data

  • BAC = Rs 25 lakh for 100 windows in 20 days, so the budget = Rs 0.25 lakh/window
  • At day 10: planned = 50 % of the work; fixed = 40 windows (40 %); expenses = Rs 9 lakh
PV=0.50×25=12.50EV=40×0.25=10.00AC=9.00\begin{aligned} PV &= 0.50 \times 25 = 12.50\\ EV &= 40 \times 0.25 = 10.00\\ AC &= 9.00 \end{aligned}

Calculation

SV=EV−PV=10.00−12.50=−2.50CV=EV−AC=10.00−9.00=1.00SPI=EV/PV=10.00/12.50=0.800CPI=EV/AC=10.00/9.00=1.111EAC=BAC/CPI=25.00/1.111=22.50ETC=EAC−AC=22.50−9.00=13.50VAC=BAC−EAC=25.00−22.50=2.50Forecast duration=20/SPI=20/0.800=25 days\begin{aligned} SV &= EV - PV = 10.00 - 12.50 = -2.50\\ CV &= EV - AC = 10.00 - 9.00 = 1.00\\ SPI &= EV/PV = 10.00/12.50 = 0.800\\ CPI &= EV/AC = 10.00/9.00 = 1.111\\ EAC &= BAC/CPI = 25.00/1.111 = 22.50\\ ETC &= EAC - AC = 22.50 - 9.00 = 13.50\\ VAC &= BAC - EAC = 25.00 - 22.50 = 2.50\\ \text{Forecast duration} &= 20/SPI = 20/0.800 = 25\ \text{days} \end{aligned}

Comment

  • Schedule: SV is negative and SPI = 0.800, so the project is behind schedule. Only 80 % of the planned work is done. At this rate the fixing will take about 25 days instead of the planned 20 days (5 days late).
  • Cost: CV is positive and CPI = 1.111, so the project is under budget. Each Rs 1 spent gives Rs 1.11 of work.
  • Forecast: if the present cost trend continues, the final cost will be Rs 22.50 lakh against the budget of Rs 25.00 lakh (variance at completion = Rs 2.50 lakh saving).

Answer: SV = -Rs 2.50 lakh, CV = Rs 1.00 lakh, SPI = 0.800, CPI = 1.111; the project is behind schedule and under budget.

Cost is favourable but progress is slow. Controlling statements: add resources or work extra shifts to recover the delay, remove bottlenecks (material, equipment, approvals), and keep the present cost discipline.

The company is late (40 windows fixed against 50 planned), but each unit costs less than budgeted (Rs 0.225 lakh against Rs 0.25 lakh).