Monitoring vs controlling; EVA concept

Short answer

Monitoring measures and reports actual progress; controlling analyses variances and acts. Earned Value Analysis uses Planned Value (PV), Earned Value (EV), and Actual Cost (AC) to compute schedule variance (SV = EV−PV) and cost variance (CV = EV−AC). SPI = EV/PV, CPI = EV/AC; SPI/CPI below 1 indicate delay or overrun, enabling corrective action.

Differentiate monitoring and controlling by explaining the project control cycle. Explain the concept of Earned Value Analysis used for controlling cost.

Monitoring and controlling

BasisMonitoringControlling
NatureObserving, measuring and reporting progressActing on the findings to bring the project back to plan
QuestionWhat is happening?What should be done about it?
OutputProgress and variance reportsCorrective action, revised plan
Stage in cycleMeasure and compareAnalyse, decide and act
AuthorityInformation gathering, any levelDecision of project manager/management

Project control cycle

+--------------+     +------------------+
| 1 Plan:      |     | 2 Implement and  |
| baseline of  |---->| measure actual   |
| time, cost,  |     | progress         |
| quality      |     +--------+---------+
+------^-------+              |
       |                      v
+------+-------+     +------------------+
| 5 Take       |     | 3 Compare actual |
| corrective   |<----| with plan and    |
| action /     |     | find variance    |
| re-plan      |     +--------+---------+
+------^-------+              |
       |                      v
       |             +------------------+
       +-------------| 4 Analyse causes |
                     | and decide       |
                     +------------------+

Monitoring covers steps 2 and 3 (measure and compare); controlling covers steps 4 and 5 (analyse and act), and the cycle is repeated at every review.

Earned Value Analysis (EVA) for cost control

EVA compares the planned value (PV), the earned value (EV) and the actual cost (AC) at a status date, so that cost and schedule performance are seen in one common unit (money).

TermOther nameMeaning
BACBudget at completionTotal approved budget of the project
PVBCWS (planned value)Budgeted cost of the work scheduled up to the date
EVBCWP (earned value)Budgeted cost of the work actually completed = % complete x BAC
ACACWP (actual cost)Actual money spent for the work done up to the date
SV=EV−PV,CV=EV−ACSPI=EVPV,CPI=EVACEAC=BACCPI,ETC=EAC−AC,VAC=BAC−EAC\begin{aligned} SV &= EV - PV, \qquad CV = EV - AC \\ SPI &= \frac{EV}{PV}, \qquad CPI = \frac{EV}{AC} \\ EAC &= \frac{BAC}{CPI}, \qquad ETC = EAC - AC, \qquad VAC = BAC - EAC \end{aligned}
IndicatorValueMeaning
SV, SPISV > 0, SPI > 1Ahead of schedule
SV = 0, SPI = 1On schedule
SV < 0, SPI < 1Behind schedule
CV, CPICV > 0, CPI > 1Under budget (cost efficient)
CV = 0, CPI = 1On budget
CV < 0, CPI < 1Over budget (cost inefficient)

Example: BAC = Rs 10 lakh; at the status date PV = Rs 5 lakh, EV = Rs 4 lakh, AC = Rs 6 lakh. SV=−1SV = -1 lakh, CV=−2CV = -2 lakh, SPI=0.80SPI = 0.80, CPI=0.67CPI = 0.67, EAC=10/0.67=15EAC = 10/0.67 = 15 lakh. The project is behind schedule and over budget, so corrective action is needed at once.