Short note: PMIS
Short answer
PMIS is an organized manual or computer-based system of people, procedures, data and tools that collects, stores, processes and reports project information for planning, monitoring and control. It gives the right information to the right person at the right time and supports progress/cost tracking, variance analysis, early warning, document control and decisions. Example: highway site data produces weekly progress, cost and variance reports.
Write a short note on Project Management Information System (PMIS).
Project Management Information System (PMIS) is an organised system (manual or computer-based) of people, procedures, data and tools that collects, stores, processes and reports information needed by project managers to plan, monitor and control a project. It gives the right information, to the right person, at the right time, in the right form.
Components
- Data input: site reports, measurement books, labour and equipment logs, material receipts, bills, test results, drawings.
- Database: schedules, budget, cost records, resource and contract data, risk register.
- Processing tools: spreadsheets, scheduling software (MS Project, Primavera), cost and EVA software.
- Output reports: progress, variance, cost, resource, quality and exception reports, dashboards.
- People and procedures: reporting formats, frequency, responsibilities.
Functions
- Planning and scheduling support; progress and cost tracking.
- Variance and trend analysis; forecasting of final cost and date.
- Early warning of problems (exception reporting).
- Document control and communication among client, consultant and contractor.
- Support for decisions, claims, and audit.
Site data -> Collect -> Store (database) -> Process
|
Decision <- Reports/Dashboard <- Analyse <----+
|
+--> Corrective action --> Site
Benefits
- Faster and better decisions with accurate, current data.
- Better coordination and communication.
- Early detection of delay and overrun.
- Less paperwork; reliable records for evaluation and claims.
Example
On a highway project the site engineer enters daily quantities of earthwork and bitumen, the store keeper enters material stock, and the accountant enters bills. The PMIS prints a weekly report showing physical progress (% complete), cost to date, and variance against the baseline, so that the manager can see which section is behind and act the same week.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- PMIS objectives and information channels · Project Engineering, chapter 4
- PMIS importance for coordination · Project Engineering, chapter 4
- Monitoring, evaluation, control must; PMIS · Project Engineering, chapter 4
- Types of projects; effect of project management · Project Engineering, chapter 1
- Project vs traditional management; external environment · Project Engineering, chapter 1
- Project management and its functions · Project Engineering, chapter 1
- Project management information system · ICT Project Management, chapter 7
- System view of project management · ICT Project Management, chapter 5
- Information in a project charter · ICT Project Management, chapter 7
- Restaurant information system requirements · Software Engineering, chapter 1