Discharge exceedance and turbine criterion

Short answer

Discharge exceedance is percentage of time a flow is equalled or exceeded, read from flow duration curve; ROR plants often designed at Q40-Q45. Turbine selection criteria: net head, specific speed, discharge variation, part-load efficiency, cavitation, sediment, cost.

What do you mean by discharge exceedance? Describe the criterion for selecting turbine in hydro-electric power plant.

Discharge exceedance

Discharge exceedance is the percentage of time a given river discharge is equalled or exceeded. It is read from the flow duration curve (FDC). For example, Q45=10Q_{45} = 10 m³/s means the river flow is 10 m³/s or more for 45% of the time (about 164 days a year).

  • Low exceedance (e.g. Q25Q_{25}) → large flow, available for a short time.
  • High exceedance (e.g. Q95Q_{95}) → small but dependable (firm) flow.
  • In Nepal, ROR projects are usually designed at about Q40Q_{40}–Q45Q_{45}; firm power is judged from Q90Q_{90}–Q95Q_{95}.
  • Exceedance is found by ranking the recorded flows in descending order and computing P=mn+1×100%P = \dfrac{m}{n+1}\times 100\% for rank mm out of nn values.
  • The choice of design exceedance is a trade-off: a lower exceedance gives more installed capacity and energy but a lower plant factor and higher cost per kW.
 Q
 |\
 | \
 |  \___ Q45
 |      \_____ Q65
 |            \______ Q95
 +---------------------> % exceedance

Criteria for selecting turbine

  1. Net head: Pelton for high head (50–1300 m), Francis for medium head (10–350 m), Kaplan/propeller for low head (2–40 m). Crossflow (Michell–Banki) and Turgo are used in small plants.
  2. Specific speed: Ns=NP/H5/4N_s = N\sqrt{P}/H^{5/4}; Pelton 10–35, Francis 60–300, Kaplan 300–1000 (metric, kW).
  3. Discharge and its variation: if flow varies greatly, choose a turbine with good part-load efficiency (Pelton, Kaplan) or use several units.
  4. Part-load operation: Francis efficiency falls below about 40–50% load; Pelton remains efficient down to 20%.
  5. Rotational speed: higher speed gives smaller generator; limited by cavitation and runaway speed.
  6. Cavitation: Thoma's coefficient fixes the setting below tailwater for reaction turbines.
  7. Sediment and abrasion: important for Himalayan rivers.
  8. Cost, efficiency, maintenance and local experience.

Example

For a site with Hnet=250H_{net} = 250 m and Q45=6Q_{45} = 6 m³/s split into two units of 3 m³/s, unit power ≈9.81×3×250×0.9≈6.6\approx 9.81 \times 3 \times 250 \times 0.9 \approx 6.6 MW. At 750 rpm, Ns=7506622/2505/4≈61N_s = 750\sqrt{6622}/250^{5/4} \approx 61, at the boundary of multi-jet Pelton and slow Francis; the Pelton is preferred if the river is silty or long part-load running is expected.

✓ Answer checked by Claude Opus 5.5 (high effort)