- 2075 Bhadra · 6 marks
Design exceedance Q45% versus Q65%
Short answer
Q45% means rated discharge is the flow equaled or exceeded 45% of the time. Q45% yields higher capacity and more total energy (mainly wet-season) but lower plant factor; Q65% gives smaller, cheaper plant with higher plant factor and lower spill risk. With a firm PPA, sellers usually prefer about Q40–Q45 for higher total revenue.
The design exceedance of hydropower plant Q45%, what does that mean? Compare Q45% with Q65% while designing hydropower plant from the perspective of power producer (seller).
Meaning of Q45%
A design exceedance of Q45% means the plant's design (rated) discharge is the flow that the river equals or exceeds 45% of the time, about days a year. The installed capacity is based on this flow:
For the other 55% of the time the plant runs at part load, following the river flow. In Nepal, NEA's power purchase practice for ROR projects has moved from about (older practice) to about –.
Comparison from the seller's (IPP) point of view
| Point | Q45% design | Q65% design |
|---|---|---|
| Design flow | Larger | Smaller |
| Installed capacity | Higher (MW) | Lower |
| Annual energy | More (extra wet-season energy) | Less |
| Plant factor | Lower (about 55–65%) | Higher (about 70–80%) |
| Capital cost | Higher (bigger waterway, units) | Lower |
| Cost per kWh | Can be higher if the extra energy is only wet-season | Lower per kWh |
| Wet-season spill/curtailment risk | Higher (NEA may curtail surplus in monsoon) | Lower |
| Dry-season share of energy | Smaller proportion | Larger proportion |
| Revenue | Higher total, if all energy is bought | Lower total, steadier |
Seller's view
- Q45 gives more MW and more total energy, which raises revenue if NEA buys all energy under a take-or-pay PPA. Bank financing and per-MW benefits also favour larger capacity.
- But most of the extra energy comes in the monsoon, when the tariff is lower (dry-season rate is higher than wet-season rate in NEA's posted rates) and when the grid already has surplus, so spillage or curtailment can reduce income.
- Q65 gives a smaller, cheaper plant with higher plant factor and lower risk, but loses wet-season energy.
- The final choice is made by comparing incremental energy and revenue against incremental cost (B/C ratio, IRR) for several exceedance values; with a firm PPA, sellers usually prefer about Q40–Q45.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Design: 95 m head plant at Q65% · Power Plant Design, chapter 4 · asked 12×
- Design: 330 m head plant, 132 kV · Power Plant Design, chapter 4 · asked 12×
- Design: 300 m head plant, GCB rating · Power Plant Design, chapter 4 · asked 11×
- Thermal versus nuclear power plant · Power Plant Design, chapter 1 · asked 2×
- Tidal versus wind power plant · Power Plant Design, chapter 1
- Design: 245 m head plant, standby generator · Power Plant Design, chapter 4 · asked 14×
- Steady state operation of hydropower plant · Power Plant Equipment, chapter 1