Criteria for distribution line route selection

Short answer

Choose the shortest practical route along roads near load clusters, with easy access and maintenance. Prefer public land, avoid unsafe terrain and crossings, maintain clearances, and allow future expansion. Final route is fixed after walk-over survey considering cost, technical limits and community views.

Describe the general criterion that should be taken into consideration for distribution (LT) line route selection in a distribution system.

The route of an LT (and HT) distribution line is the path along which poles are erected. A good route gives the shortest, safest and cheapest line that serves the consumers well and is easy to maintain.

General criteria

  1. Shortest practical length: a route close to a straight line between the transformer and load clusters reduces cost, voltage drop and losses. Avoid unnecessary bends, since each angle point needs a stronger pole with stays.
  2. Follow roads and tracks: lines along the road side (within the road right-of-way) give easy access for construction, operation and maintenance, and avoid crossing private land.
  3. Proximity to consumers: the line should pass near the houses to keep service drops short (typically within about 30–40 m), reducing service cable cost and losses.
  4. Load balance: arrange feeders so that load is shared equally among phases and feeders, and so the transformer remains near the load centre.
  5. Right-of-way and land issues: prefer public land; minimise compensation, disputes and tree cutting. Avoid passing over buildings.
  6. Safety clearances: maintain statutory clearances from buildings, roads, footpaths, telecom lines and other power lines (as per Nepal Electricity Regulations); avoid schools, playgrounds and fuel stations.
  7. Terrain and soil: avoid landslide-prone slopes, river banks, flood plains, marshy and unstable ground; choose firm ground for pole foundations.
  8. Crossings: minimise crossings of rivers, highways, railways and other lines; cross at right angles where needed.
  9. Environment and aesthetics: avoid forests, heritage sites and protected areas; use ABC or underground cable in sensitive or crowded areas.
  10. Future expansion: leave room for new consumers and for future upgrading (e.g. to three-phase or larger conductors).
  11. Span and pole positions: keep uniform spans (about 40–50 m for LT) and place poles where they will not obstruct traffic or drainage.

The final route is fixed after a walk-over survey, considering cost, technical limits and the views of the local community.