- 2072 Magh · 2 marks
Justify: trending method for large area forecast
Short answer
Large area loads grow smoothly as random small-area variations average out, allowing curve fitting on long historical records. Only total magnitude is needed for generation/transmission planning, so the trending method is quick, cheap and sufficient.
Justify the following statement in brief: The trending method of the load forecast is more suitable for large area load forecast.
The statement is correct.
The trending method fits a curve (linear, exponential or polynomial) to past load data and extends it into the future. It suits large areas (a whole utility, region or country) because:
- The load of a large area is the sum of many small areas at different stages of growth. Their random, step-like changes average out, so the total grows smoothly and steadily, which a simple curve can follow.
- Large areas have long, reliable load records (years of peak demand and energy sales) to fit the curve.
- Only the total amount of load is needed for generation and transmission planning, not its exact location.
- It is quick, cheap and needs no detailed land-use or end-use data.
For small areas, load stays near zero and then jumps (S-curve), and history is short, so trending gives poor results there; simulation (land-use) methods are used instead.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- T/F: simulation method for small area forecast · Transmission and Distribution System Design, chapter 6 · asked 2×
- Justify higher voltage/more circuits for more power · Transmission and Distribution System Design, chapter 2
- T/F: radial more reliable than network · Transmission and Distribution System Design, chapter 5 · asked 2×
- T/F: grid connected system more stable · Transmission and Distribution System Design, chapter 1
- T/F: higher voltage more economical · Transmission and Distribution System Design, chapter 2
- Small area forecasting with load growth curve · Transmission and Distribution System Design, chapter 6
- Define load forecast · Power Plant Design, chapter 2 · asked 3×
- Quality costs more, lack costs even more · Project Engineering, chapter 4 · asked 2×
- Large starting current; 3-point starter · Electrical Machine, chapter 4
- Hydrological losses statement, factors affecting evaporation · Engineering Hydrology, chapter 3
All Transmission and Distribution System Design chapter 6 questions →