Proposal for communication technology centre

Short answer

Title page: Proposal for Communication Technology Centre at Dhobighat, submitted to the Director of National Institute of Computer Education. Technical section: Two training halls, video-conferencing room, recording studio, 20 computers, LMS, and courses; setup in 4 months. Cost estimate: Rs. 91,35,000 including 5% contingency.

Assume that as a Project Development Officer you have been asked by the National Institute of Computer Education, Kathmandu, to set up a Communication Technology Centre at Dhobighat, Kathmandu for training professionals in the use of latest technological aids for face-to-face and distance communication. Write a technical proposal to be submitted to the Director of the Institute. Prepare only title page, technical section and cost estimate of your proposal.

Title page

                         PROPOSAL

ESTABLISHMENT OF A COMMUNICATION TECHNOLOGY CENTRE AT
DHOBIGHAT, KATHMANDU

Submitted to:
The Director
National Institute of Computer Education
Kathmandu

Submitted by:
Er. Roshan Maharjan
Project Development Officer

15 December 2026

Technical section

The centre will train professionals in the use of the latest tools for face-to-face and distance communication.

  1. Training halls. Two halls of 30 seats each for face-to-face training, equipped with projectors, smart boards and a sound system.
  2. Video-conferencing room. A room for 15 persons with HD cameras and a codec for live online sessions with remote participants, in addition to a Learning Management System (LMS) for distance courses.
  3. Studio. A small studio to record lectures and make video tutorials, with a lighting and microphone set.
  4. Computer lab. Twenty computers with software for presentations, e-mail, collaboration and content creation.
  5. Network. A 100 Mbps fibre connection, Wi-Fi and a firewall, with backup power.
  6. Courses. Short courses of two to four weeks on virtual meetings, e-learning, presentation and technical writing, and digital media.
  7. Work plan. Building renovation: 6 weeks; equipment purchase and installation: 8 weeks; staff training and trial: 2 weeks; start of the first batch in about 4 months.
  8. Staff. One manager, two trainers, one technician and one office assistant.

Cost estimate

S.N.ItemAmount (Rs.)
1Building rent and renovation for the centre (1 year)12,00,000
2Video-conferencing system (cameras, screens, codec)18,00,000
3Computers and servers (20 units)19,00,000
4Audio-visual equipment (projectors, microphones, smart board)8,50,000
5Studio and recording equipment for distance learning12,00,000
6Internet bandwidth and networking (1 year)6,00,000
7Furniture and air-conditioning6,50,000
8Staff training and administration5,00,000
Sub-total87,00,000
Contingency (5%)4,35,000
Grand total91,35,000

The above cost covers the first year; income from course fees will support running costs from the second year.