Contingencies and work charged establishment
Short answer
Contingency is a lump-sum allowance (3–5% of estimated cost) for unforeseen small expenses, sanctioned by competent authority. Work-charged establishment consists of temporary staff (supervisors, watchmen, clerks) paid from work cost, with an allowance of 1.5–2.5% added to the estimate.
What do you mean by contingencies and work charged establishment?
Contingencies
Contingency is a lump-sum allowance (usually 3 to 5% of the estimated cost) added to the estimate to cover small expenses that cannot be foreseen at the time of estimating: small changes in quantity, minor extra items, errors and omissions, and temporary rises in cost. It is spent only with the sanction of the competent authority. In some practice it also covers items such as stationery, travel and testing.
Work-charged establishment
Work-charged establishment means the temporary staff engaged for a specific work and paid from the cost of that work rather than from the regular office budget. These include supervisors, overseers, store keepers, watchmen (chowkidar), chainmen, mates and clerks employed for the project period. An allowance of about 1.5 to 2.5% of the estimated cost is added to the estimate for it. Such staff are released when the work ends.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Work breakdown for frame structure quantities · Estimating and Costing, chapter 2
- Preliminary estimate: residential, 500 m² carpet · Estimating and Costing, chapter 3
- Preliminary estimate: office, 3275 m² carpet · Estimating and Costing, chapter 3
- Preliminary estimate: polytechnic, 800 students · Estimating and Costing, chapter 3
- Masonry work, materials for 20 cum brickwork · Building Technology, chapter 3
- Contour interpolation, method for large work · Surveying II, chapter 4
- Statement of work · ICT Project Management, chapter 7
- Work breakdown structure (WBS) · ICT Project Management, chapter 7