Skip to main content

Materials: 10 m³ brick 1:6, 10 m³ PCC 1:3:6

Short answer

i) 10 m³ brickwork 1:6 (brick 230x110x55 mm, 10 mm joint): 5,342 bricks, 13.4 bags cement, 2.79 m³ sand. ii) 10 m³ PCC 1:3:6: dry factor 1.54, cement 44.4 bags, sand 4.62 m³, aggregate 9.24 m³.

Calculate the quantities of materials required for the following works: i) 10 m³ brick masonry in 1:6 cement mortar ii) 10 m³ PCC (1:3:6) in foundation.

Assumptions: dry volume 1.54 × wet for concrete and 1.27 × wet for mortar; 1 m³ cement = 28.8 bags. The brick size is not given, so 230 × 110 × 55 mm with 10 mm joints is taken.

(i) 10 m³ brickwork in 1:6 mortar

  • Brick with mortar =0.240×0.120×0.065=1872.0×10−6= 0.240 \times 0.120 \times 0.065 = 1872.0\times 10^{-6} m³; bricks per m³ =1/(1872.0×10−6)=534.19= 1/(1872.0\times10^{-6}) = 534.19
  • Bricks for 10.00 m³ =534.19×10.00=5,342= 534.19 \times 10.00 = 5,342 nos
  • Volume of bricks only =0.230×0.110×0.055=1391.5×10−6= 0.230\times0.110\times0.055 = 1391.5\times10^{-6} m³ each; wet mortar per m³ =1−534.19×1391.5×10−6=0.2567= 1 - 534.19\times1391.5\times10^{-6} = 0.2567 m³
  • Wet mortar for 10.00 m³ =2.567= 2.567 m³; dry =1.27×2.567=3.260= 1.27\times2.567 = 3.260 m³
  • Cement =1/7×3.260=0.466= 1/7\times3.260 = 0.466 m³ =13.4= 13.4 bags
  • Sand =6/7×3.260=2.794= 6/7\times3.260 = 2.794 m³

(ii) 10 m³ PCC (1:3:6)

  • Wet volume =10.000= 10.000 m³; dry volume =1.54×10.000=15.400= 1.54 \times 10.000 = 15.400 m³ (sum of ratio =10= 10)
  • Cement =1/10×15.400=1.540= 1/10 \times 15.400 = 1.540 m³ =1.540×28.8=44.4= 1.540 \times 28.8 = 44.4 bags (50 kg)
  • Sand =3/10×15.400=4.620= 3/10 \times 15.400 = 4.620 m³
  • Coarse aggregate =6/10×15.400=9.240= 6/10 \times 15.400 = 9.240 m³

Answer: (i) bricks 5,342, cement 13.4 bags, sand 2.79 m³. (ii) cement 44.4 bags, sand 4.62 m³, aggregate 9.24 m³.