Short note: Centre line method
Short answer
Centre line method uses total centre-line length corrected by deducting half the wall width for each T-junction (cross-junction counts as two). Multiply corrected length by width and depth. For a 4 x 3 m room with 0.23 m wall, trench volume is 13.43 m3.
Write a short note on the centre line method.
The centre line method is a quick way of finding the quantities of earthwork, foundation and walls in a building whose walls have the same section.
Procedure
- Find the total centre-line length of all the walls (main and partitions), measured along the middle of the walls.
- Deduct for the junctions where walls meet: each T-junction takes away half of the width of the wall (the part counted twice); a cross-junction deducts the same on each side, i.e. it counts as two T-junctions.
- Multiply the corrected length by the width and the depth of each section (trench, PCC, footing, plinth masonry, superstructure).
Formula
where is the number of T-junctions (a cross-junction counts as two) and the width of the wall at that level.
Example
For a room 4 m x 3 m (clear) with a 0.23 m wall: m. A partition with two T-junctions would deduct m. The trench volume = m³.
Merits and limits
It is fast and simple, and suited to uniform rectangular buildings; it is not accurate where the wall sections differ, for which the long wall-short wall method is used.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Road earthwork, grades 1 in 120 and 1 in 90 (0-120) · Estimating and Costing, chapter 6 · asked 2×
- Road earthwork, 80 m length (v) · Estimating and Costing, chapter 6 · asked 2×
- Hill road earthwork, chainage 0-150 (50 m) · Estimating and Costing, chapter 6
- Hill road earthwork, km 8.50 to km 9.00 · Estimating and Costing, chapter 6
- Hill road earthwork with cross sections · Estimating and Costing, chapter 6
- Transition curve about centre line, 65 kmph · Transportation Engineering I, chapter 3
- Locating the instantaneous centre · Engineering Mechanics, chapter 5
- Shear centre of a channel section · Mechanics of Solids, chapter 10
- Audible noise of 735 kV line at 30 m · High Voltage Engineering, chapter 5 · asked 4×