- 2080 Bhadra · 4 marks
Optimizing plant capacity of a RoR project
Short answer
Prepare the flow duration curve, compute power and annual energy for trial design discharges, then calculate annual benefit (energy × price) and annualized cost (fixed + variable). Optimum is maximum net benefit or where marginal benefit equals marginal annual cost, so the last added kW pays for itself.
How do you optimize the plant capacity of a RoR project? Discuss.
The installed capacity of a RoR plant is optimised by comparing the extra cost and the extra benefit of each increase in capacity. Since flow varies throughout the year, a bigger plant uses the large flow only for a short time, so there is an optimum point.
Procedure
- Prepare the flow duration curve (FDC) from the long-term flow series (after the environmental release).
- Select a number of trial design discharges (e.g. , , ...). For each, compute the power and the energy:
- Compute annual benefit = energy × price (firm and secondary energy may have different prices).
- Compute annual cost = (fixed cost + variable cost × P) × capital recovery factor + O&M. Fixed cost includes the headworks, civil structures, access and so on; variable cost is proportional to the capacity (turbine, generator, penstock).
- Plot the net benefit (benefit − cost), the benefit/cost ratio and the marginal values against the capacity.
Criterion
- Maximum net benefit (NPV), or
- Marginal benefit = marginal cost: increase capacity until the extra benefit from the last kW (= price × energy produced by it during the time it is used) equals its extra annual cost. Beyond this point the machines run only a few weeks per year and do not pay back.
Other considerations: the cost per kW, the plant factor (usually 50-70% for RoR), the grid demand, the risk and the possibility of staged development.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Optimize capacity by marginal cost-benefit · Hydropower Engineering, chapter 3
- RoR best installed capacity (USD 2795 million) · Hydropower Engineering, chapter 3
- Load duration curve; diesel plant; ROR flow duration · Hydropower Engineering, chapter 3
- RoR installed capacity without pondage and with peaking · Hydropower Engineering, chapter 3
- RoR best installed capacity (NRs, 45 years) · Hydropower Engineering, chapter 3
- RoR best installed capacity (USD 1200 million) · Hydropower Engineering, chapter 3
- Intake site selection for RoR plant · Hydro Power, chapter 5
- ROR versus PROR hydropower plants · Power Plant Design, chapter 3
- Design: 360 m head plant, 132 kV · Power Plant Design, chapter 4 · asked 5×
- Design: 260 m head plant, generator lead · Power Plant Design, chapter 4 · asked 5×