Frequency of flushing of settling basin

Short answer

Deposit volume per unit water: vs = (0.40×2.0)/1325 ≈ 6.04×10⁻⁴ m³ deposit/m³ water. Storage 0.1 Vb, water to fill = 165.6 Vb, so flush every 165.6 detention times (e.g., ~27.6 h for 10‑min detention).

If you have allocated about 10% volume for sediment storage and the overall trapping efficiency of the settling basin is 40%, find out the frequency of flushing of the settling basin when the sediment concentration is 2000 ppm.

Given: sediment storage =10%=10\% of the basin volume VbV_b; overall trap efficiency η=40%\eta=40\%; sediment concentration C=2000C=2000 ppm =2.0=2.0 kg/m³. Assumption: the settled sediment has a bulk density of ρb=2650×0.5=1325\rho_b=2650\times0.5=1325 kg/m³ (particle density 2650 kg/m³, packing factor 0.5).

Step 1: Volume of sediment trapped per m³ of water

vs=η Cρb=0.40×2.01325=6.038×10−4 m3 of deposit per m3 of waterv_s=\frac{\eta\,C}{\rho_b}=\frac{0.40\times2.0}{1325}=6.038 \times 10^{-4}\ \text{m}^3\ \text{of deposit per m}^3\ \text{of water}

Step 2: Storage volume

Vst=0.10 VbV_{st}=0.10\,V_b

Step 3: Volume of water that can pass before the storage is full

Vw=Vstvs=0.10 Vb6.038×10−4=165.6 VbV_w=\frac{V_{st}}{v_s}=\frac{0.10\,V_b}{6.038 \times 10^{-4}}=165.6\,V_b

Step 4: Frequency of flushing

The water passes through the basin at the rate QQ, so the time between flushes is

T=VwQ=165.6 VbQ=165.6 tdT=\frac{V_w}{Q}=165.6\,\frac{V_b}{Q}=165.6\,t_d

where td=Vb/Qt_d=V_b/Q is the detention time of the basin.

So the basin should be flushed once after about 165.6 detention periods (about every 166 times the time that water takes to pass through it). For example, if the detention time is 10 minutes, then T=1656T=1656 minutes ≈27.6\approx27.6 hours (about 0.9 flushes per day); if td=5t_d=5 minutes, T≈13.8T\approx13.8 hours.

Answer: flush every ≈165.6 Vb/Q\approx165.6\,V_b/Q (about 166 detention times; e.g. about 27.6 h for a 10-minute detention time).