- Asked 2/21
- 2080 Baishakh · 8 marks
Surge numerical: 4 m tunnel, 4000 m, 20 m³/s
Short answer
Tunnel velocity 1.592 m/s, friction loss 2.32 m and frictionless amplitude 12.86 m. With instantaneous closure the maximum upsurge is 11.36 m above reservoir level; first downswing is 9.36 m below. Oscillation period is 317.2 s, about 5.3 min.
In a hydropower project the headrace tunnel of 4.0 m diameter and 4000 m length carries 20 m³/s discharge to the surge tank of 10 m diameter. The penstock from the surge tank to the power house has 3.2 m diameter and 700 m length. Considering the case of instantaneous closure, find the maximum height of the surge tank required and the time period of oscillation of wave. Assume friction factor = 0.018.
Method used
Let the tunnel have area , length , diameter and friction factor ; the tank has area .
- Tunnel velocity ; steady friction loss .
- Frictionless amplitude: .
- Upsurge with friction (full load rejection), measured above reservoir level, from the equation of motion and continuity:
- The following down-surge is found by integrating the reversed-flow equations step by step (below reservoir level).
- Period of mass oscillation: .
Calculation
, , m, .
- m/s
- m
- m
Instantaneous closure of the turbine gates means complete rejection of the discharge, so the water rises in the tank. The penstock (3.2 m, 700 m) lies downstream of the tank, so it does not affect the tank oscillation.
Maximum height of surge tank
From the upsurge equation with friction: m above reservoir level (the frictionless value is 12.86 m).
The tank must therefore extend at least 11.4 m above the reservoir water level (plus a freeboard of about 1 to 2 m). The first downswing is 9.36 m below reservoir level.
Time period
Answer: maximum upsurge height m above reservoir level; s.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Surge numerical: 4.5 m tunnel, 2500 m, 25 m³/s · Hydropower Engineering, chapter 6 · asked 2×
- Surge numerical: 13 m tank, 1.8 km tunnel · Hydropower Engineering, chapter 6
- Surge and water hammer: 45 m³/s, 20 m surge tank · Hydropower Engineering, chapter 6 · asked 2×
- Surge tank: tunnel 5 m dia, 28 cumec · Hydropower Engineering, chapter 6
- Surge and water hammer: 60 m³/s, 30 m surge tank · Hydropower Engineering, chapter 6 · asked 2×
- Surge and water hammer: 25 m³/s, 15 m surge tank · Hydropower Engineering, chapter 6 · asked 3×
- Surge tank: 7.5 m³/s through 2.5 m tunnel · Hydropower Engineering, chapter 6
- Surge tank objectives and economic penstock diameter factors · Hydro Power, chapter 5
- Water hammer in penstock and surge tank · Power Plant Equipment, chapter 1 · asked 2×
- Pressure rise for instantaneous closure, elastic pipe · Hydraulics, chapter 4