- 2076 Chaitra · 7+3+2 marks
Uniform draw-off and reservoir capacity
Short answer
Total inflow of the driest year is 28.75×10⁶ m³; maximum uniform draw-off is 2.396×10⁶ m³/month, requiring a reservoir capacity of 10.52×10⁶ m³ and minimum initial storage of 6.46×10⁶ m³. With a capacity of 8×10⁶ m³ and initial storage of 4×10⁶ m³, the maximum draw-off is 2.036×10⁶ m³/month and annual spillage is 1.143×10⁶ m³.
The monthly flows of a stream over the period of the driest year on record are as shown below:
| Month | J | F | M | A | M | J | J | A | S | O | N | D |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Flow (×10⁶ m³) | 4.0 | 2.25 | 5.0 | 1.25 | 0.5 | 0.75 | 0.5 | 0.75 | 1.25 | 1.25 | 5.0 | 6.25 |
(i) Estimate the maximum possible uniform draw-off from this stream and determine the reservoir capacity to achieve the uniform draw-off and the minimum initial storage to maintain the demand. (ii) If the reservoir has only a total capacity of 8×10⁶ m³ with an initial storage of 4×10⁶ m³, determine (a) the maximum possible uniform draw-off and (b) the spillage.
Volumes are in 10⁶ m³ per month.
(i) Maximum uniform draw-off, reservoir capacity, minimum initial storage
Total inflow of the driest year . The maximum uniform draw-off possible in the year is the mean monthly inflow:
Mass-curve table (cumulative of inflow − draw-off, starting from January):
| Month | Inflow | Draw-off | Net | Cumulative |
|---|---|---|---|---|
| J | 4.0 | 2.396 | +1.604 | +1.604 |
| F | 2.25 | 2.396 | -0.146 | +1.458 |
| M | 5.0 | 2.396 | +2.604 | +4.062 |
| A | 1.25 | 2.396 | -1.146 | +2.917 |
| M | 0.5 | 2.396 | -1.896 | +1.021 |
| J | 0.75 | 2.396 | -1.646 | -0.625 |
| J | 0.5 | 2.396 | -1.896 | -2.521 |
| A | 0.75 | 2.396 | -1.646 | -4.167 |
| S | 1.25 | 2.396 | -1.146 | -5.313 |
| O | 1.25 | 2.396 | -1.146 | -6.458 |
| N | 5.0 | 2.396 | +2.604 | -3.854 |
| D | 6.25 | 2.396 | +3.854 | -0.000 |
- The cumulative reaches its highest value (+4.062) at the end of March and its lowest (-6.458) at the end of October.
- Minimum initial storage (January 1st) needed so that the demand is never short: m³.
- Reservoir capacity = peak − trough m³.
(ii) Capacity 8 × 10⁶ m³, initial storage 4 × 10⁶ m³
The reservoir is smaller than 10.52, so some water is spilled when it is full and the draw-off must be reduced so that the storage never becomes negative. Trial routing gives the largest draw-off for which the reservoir just reaches zero (in October):
| Month | Inflow | Draw-off | Storage before spill | Spill | Storage end |
|---|---|---|---|---|---|
| J | 4.0 | 2.036 | 5.964 | 0.000 | 5.964 |
| F | 2.25 | 2.036 | 6.179 | 0.000 | 6.179 |
| M | 5.0 | 2.036 | 9.143 | 1.143 | 8.000 |
| A | 1.25 | 2.036 | 7.214 | 0.000 | 7.214 |
| M | 0.5 | 2.036 | 5.679 | 0.000 | 5.679 |
| J | 0.75 | 2.036 | 4.393 | 0.000 | 4.393 |
| J | 0.5 | 2.036 | 2.857 | 0.000 | 2.857 |
| A | 0.75 | 2.036 | 1.571 | 0.000 | 1.571 |
| S | 1.25 | 2.036 | 0.786 | 0.000 | 0.786 |
| O | 1.25 | 2.036 | -0.000 | 0.000 | -0.000 |
| N | 5.0 | 2.036 | 2.964 | 0.000 | 2.964 |
| D | 6.25 | 2.036 | 7.179 | 0.000 | 7.179 |
(a) Maximum uniform draw-off m³/month ( m³/s).
(b) Spillage m³ in the year (in March, when the reservoir is full).
Answer: (i) draw-off = 2.396 Mm³/month, capacity = 10.52 Mm³, minimum initial storage = 6.46 Mm³. (ii) (a) draw-off = 2.036 Mm³/month; (b) spillage = 1.14 Mm³.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Installed capacity, energy and daily peaking reservoir (2079) · Hydropower Engineering, chapter 3 · asked 2×
- Installed capacity, energy and daily peaking reservoir (2072) · Hydropower Engineering, chapter 3 · asked 2×
- Full regulation: reservoir, capacity, annual energy · Hydropower Engineering, chapter 3
- Storage for mean annual flow (monthly volumes) · Hydropower Engineering, chapter 3
- Minimum reservoir capacity and wasted water · Hydropower Engineering, chapter 3
- RoR best installed capacity (USD 1200 million) · Hydropower Engineering, chapter 3
- 24-hr maximum rainfall for 50-year return period · Engineering Hydrology, chapter 6
- Contraction to 1.25 m: is flow possible? · Hydraulics, chapter 7
- Impounded reservoir, 6202 million L per month · Water Supply Engineering, chapter 2 · asked 2×
- Impounded reservoir, 9688 million L per month · Water Supply Engineering, chapter 2 · asked 2×