CPM components (AOA), 9 activities

Short answer

AOA network with one dummy; forward/backward pass gives 13 weeks. Two critical paths A-C-F-I and B-E-H-I; critical activities A, B, C, E, F, H, I; all floats computed, with zero total float on critical activities.

Find all components of CPM from the following information using the AOA method.

ActivityDuration (week)Predecessor
A3-
B2-
C4A
D3B
E3B
F3C
G2C, D
H5E
I3F, G, H

The components of CPM are: the network, event times (TE, TL), activity times (EST, EFT, LST, LFT), floats (TF, FF, Int.F, Ind.F), the critical path and the project duration. All are found below with the activity-on-arrow (AOA) method.

Notation: EST/EFT = earliest start/finish, LST/LFT = latest start/finish, TF = total float, FF = free float, Int.F = interfering float, Ind.F = independent float.

Network diagram (activity-on-arrow)

Each activity is an arrow with its duration in brackets (weeks). Events are circled numbers; dashed arrows are dummy activities (zero duration) that show dependencies only.

(1) --A(3)--> (2)
(1) --B(2)--> (3)
(2) --C(4)--> (4)
(3) --E(3)--> (5)
(3) --D(3)--> (6)
(4) - - dummy - -> (6)
(4) --F(3)--> (7)
(5) --H(5)--> (7)
(6) --G(2)--> (7)
(7) --I(3)--> (8)

The network has 8 events and 1 dummy activity. Start event is (1) and the end event is (8).

Forward pass (EST and EFT)

Rule: EST = largest EFT of the preceding activities (0 for start activities); EFT = EST + D.

  • A: EST = 0; EFT = 0 + 3 = 3
  • B: EST = 0; EFT = 0 + 2 = 2
  • D: EST = EFT of B = 2; EFT = 2 + 3 = 5
  • E: EST = EFT of B = 2; EFT = 2 + 3 = 5
  • C: EST = EFT of A = 3; EFT = 3 + 4 = 7
  • H: EST = EFT of E = 5; EFT = 5 + 5 = 10
  • F: EST = EFT of C = 7; EFT = 7 + 3 = 10
  • G: EST = max(C:7, D:5) = 7; EFT = 7 + 2 = 9
  • I: EST = max(F:10, G:9, H:10) = 10; EFT = 10 + 3 = 13

Project duration = largest EFT = 13 weeks.

Backward pass (LFT and LST)

Rule: LFT = smallest LST of the succeeding activities (project duration for end activities); LST = LFT - D.

  • I: LFT = project duration = 13; LST = 13 - 3 = 10
  • G: LFT = LST of I = 10; LST = 10 - 2 = 8
  • F: LFT = LST of I = 10; LST = 10 - 3 = 7
  • H: LFT = LST of I = 10; LST = 10 - 5 = 5
  • C: LFT = min(F:7, G:8) = 7; LST = 7 - 4 = 3
  • E: LFT = LST of H = 5; LST = 5 - 3 = 2
  • D: LFT = LST of G = 8; LST = 8 - 3 = 5
  • B: LFT = min(D:5, E:2) = 2; LST = 2 - 2 = 0
  • A: LFT = LST of C = 3; LST = 3 - 3 = 0

Floats

  • Total float TF=LST−EST=LFT−EFTTF = LST - EST = LFT - EFT
  • Free float FF=min⁡(EST of successors)−EFTFF = \min(\text{EST of successors}) - EFT
  • Interfering float IntF=TF−FFIntF = TF - FF
  • Independent float IndF=max⁡(0, min⁡(EST of successors)−max⁡(LFT of predecessors)−D)IndF = \max\left(0,\ \min(\text{EST of successors}) - \max(\text{LFT of predecessors}) - D\right)

Result table

ActivityDESTEFTLSTLFTTFFFInt.FInd.F
A303030000
B202020000
C437370000
D325583212
E325250000
F37107100000
G2798101100
H55105100000
I3101310130000

Event times (TE from the forward pass, TL from the backward pass):

EventTE (earliest)TL (latest)Slack
1000
2330
3220
4770
5550
6781
710100
813130

Critical path and project duration

  • Critical activities (TF = 0): A, B, C, E, F, H, I
  • Critical path: A - C - F - I (= 3+4+3+3 = 13 weeks)
  • Critical path: B - E - H - I (= 2+3+5+3 = 13 weeks)
  • There are two critical paths of the same length, so a delay on either one delays the project.

Answer: project duration = 13 weeks; critical paths = A - C - F - I and B - E - H - I