CPM components (AOA), 13 activities (months)
Short answer
Using AOA forward/backward pass, all CPM components (network, event/activity times, floats) are determined. Project duration is 14 months. Critical paths are B-E-I-L and B-E-K-M, each with total duration 14 months.
Find all the components of CPM from the following information. Use the AOA method.
| Activity | Duration (month) | Predecessor | Successor |
|---|---|---|---|
| A | 1 | - | C, D |
| B | 3 | - | E |
| C | 2 | A | F, G |
| D | 2 | A | H |
| E | 5 | B | I, J, K |
| F | 1 | C | I |
| G | 3 | C | I, J, K |
| H | 3 | D | I, J, K |
| I | 5 | E, F, G, H | L |
| J | 1 | E, G, H | L |
| K | 4 | E, G, H | M |
| L | 1 | I, J | - |
| M | 2 | K | - |
The components of CPM are: the network, event times (TE, TL), activity times (EST, EFT, LST, LFT), floats (TF, FF, Int.F, Ind.F), the critical path and the project duration. All are found below with the activity-on-arrow (AOA) method.
Notation: EST/EFT = earliest start/finish, LST/LFT = latest start/finish, TF = total float, FF = free float, Int.F = interfering float, Ind.F = independent float.
Network diagram (activity-on-arrow)
Each activity is an arrow with its duration in brackets (months). Events are circled numbers; dashed arrows are dummy activities (zero duration) that show dependencies only.
(1) --A(1)--> (2)
(1) --B(3)--> (3)
(2) --C(2)--> (4)
(2) --D(2)--> (5)
(3) --E(5)--> (6)
(4) --G(3)--> (6)
(4) --F(1)--> (8)
(5) --H(3)--> (6)
(6) --K(4)--> (7)
(6) - - dummy - -> (8)
(6) --J(1)--> (9)
(7) --M(2)--> (10)
(8) --I(5)--> (9)
(9) --L(1)--> (10)
The network has 10 events and 1 dummy activity. Start event is (1) and the end event is (10).
Forward pass (EST and EFT)
Rule: EST = largest EFT of the preceding activities (0 for start activities); EFT = EST + D.
- A: EST = 0; EFT = 0 + 1 = 1
- B: EST = 0; EFT = 0 + 3 = 3
- C: EST = EFT of A = 1; EFT = 1 + 2 = 3
- D: EST = EFT of A = 1; EFT = 1 + 2 = 3
- E: EST = EFT of B = 3; EFT = 3 + 5 = 8
- F: EST = EFT of C = 3; EFT = 3 + 1 = 4
- G: EST = EFT of C = 3; EFT = 3 + 3 = 6
- H: EST = EFT of D = 3; EFT = 3 + 3 = 6
- I: EST = max(E:8, F:4, G:6, H:6) = 8; EFT = 8 + 5 = 13
- J: EST = max(E:8, G:6, H:6) = 8; EFT = 8 + 1 = 9
- K: EST = max(E:8, G:6, H:6) = 8; EFT = 8 + 4 = 12
- M: EST = EFT of K = 12; EFT = 12 + 2 = 14
- L: EST = max(I:13, J:9) = 13; EFT = 13 + 1 = 14
Project duration = largest EFT = 14 months.
Backward pass (LFT and LST)
Rule: LFT = smallest LST of the succeeding activities (project duration for end activities); LST = LFT - D.
- L: LFT = project duration = 14; LST = 14 - 1 = 13
- M: LFT = project duration = 14; LST = 14 - 2 = 12
- K: LFT = LST of M = 12; LST = 12 - 4 = 8
- J: LFT = LST of L = 13; LST = 13 - 1 = 12
- I: LFT = LST of L = 13; LST = 13 - 5 = 8
- H: LFT = min(I:8, J:12, K:8) = 8; LST = 8 - 3 = 5
- G: LFT = min(I:8, J:12, K:8) = 8; LST = 8 - 3 = 5
- F: LFT = LST of I = 8; LST = 8 - 1 = 7
- E: LFT = min(I:8, J:12, K:8) = 8; LST = 8 - 5 = 3
- D: LFT = LST of H = 5; LST = 5 - 2 = 3
- C: LFT = min(F:7, G:5) = 5; LST = 5 - 2 = 3
- B: LFT = LST of E = 3; LST = 3 - 3 = 0
- A: LFT = min(C:3, D:3) = 3; LST = 3 - 1 = 2
Floats
- Total float
- Free float
- Interfering float
- Independent float
Result table
| Activity | D | EST | EFT | LST | LFT | TF | FF | Int.F | Ind.F |
|---|---|---|---|---|---|---|---|---|---|
| A | 1 | 0 | 1 | 2 | 3 | 2 | 0 | 2 | 0 |
| B | 3 | 0 | 3 | 0 | 3 | 0 | 0 | 0 | 0 |
| C | 2 | 1 | 3 | 3 | 5 | 2 | 0 | 2 | 0 |
| D | 2 | 1 | 3 | 3 | 5 | 2 | 0 | 2 | 0 |
| E | 5 | 3 | 8 | 3 | 8 | 0 | 0 | 0 | 0 |
| F | 1 | 3 | 4 | 7 | 8 | 4 | 4 | 0 | 2 |
| G | 3 | 3 | 6 | 5 | 8 | 2 | 2 | 0 | 0 |
| H | 3 | 3 | 6 | 5 | 8 | 2 | 2 | 0 | 0 |
| I | 5 | 8 | 13 | 8 | 13 | 0 | 0 | 0 | 0 |
| J | 1 | 8 | 9 | 12 | 13 | 4 | 4 | 0 | 4 |
| K | 4 | 8 | 12 | 8 | 12 | 0 | 0 | 0 | 0 |
| L | 1 | 13 | 14 | 13 | 14 | 0 | 0 | 0 | 0 |
| M | 2 | 12 | 14 | 12 | 14 | 0 | 0 | 0 | 0 |
Event times (TE from the forward pass, TL from the backward pass):
| Event | TE (earliest) | TL (latest) | Slack |
|---|---|---|---|
| 1 | 0 | 0 | 0 |
| 2 | 1 | 3 | 2 |
| 3 | 3 | 3 | 0 |
| 4 | 3 | 5 | 2 |
| 5 | 3 | 5 | 2 |
| 6 | 8 | 8 | 0 |
| 7 | 12 | 12 | 0 |
| 8 | 8 | 8 | 0 |
| 9 | 13 | 13 | 0 |
| 10 | 14 | 14 | 0 |
Critical path and project duration
- Critical activities (TF = 0): B, E, I, K, M, L
- Critical path: B - E - I - L (= 3+5+5+1 = 14 months)
- Critical path: B - E - K - M (= 3+5+4+2 = 14 months)
- There are two critical paths of the same length, so delay on either one delays the project.
Answer: project duration = 14 months; critical path = B - E - I - L ; B - E - K - M
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- CPM components (AOA), 10 activities · Project Engineering, chapter 3 · asked 5×
- CPM components (AOA), activities A to I · Project Engineering, chapter 3 · asked 4×
- CPM components (AOA), 9 activities · Project Engineering, chapter 3 · asked 4×
- CPM components, 9 activities with successors · Project Engineering, chapter 3 · asked 3×
- CPM network, 13 activities (A to M) · Project Engineering, chapter 3 · asked 5×
- CPM network, 13 activities (A=2 to M=7) · Project Engineering, chapter 3 · asked 5×
- CPM network, hydropower project (months) · Project Engineering, chapter 3
- CPM precedence diagram, 9 activities · Project Engineering, chapter 3
- CPM network, 9 activities (A=3 to I=1) · Project Engineering, chapter 3 · asked 5×
- CPM network, 9 activities (A=5 to I=2) · Project Engineering, chapter 3 · asked 5×