Road earthwork, four lane NRS-1070
Short answer
From cross sections with given cross slopes, compute cut and fill areas at each chainage. Apply mean area method over 30 m intervals. Total earthwork: cutting 1315.99 m³, filling 610.78 m³.
Workout the quantities of earthwork in embankment and cutting based on the data provided below. Formation width of road: Dedicated four lane width based on NRS-1070. Side slope in embankment and excavation is 1:2 and 1:1.5 respectively.
| Chainage | 0+000 | 0+030 | 0+060 | 0+090 | 0+120 | 0+150 | 0+180 |
|---|---|---|---|---|---|---|---|
| RL of GL (m) | 152.00 | 152.35 | 152.60 | 152.80 | 153.00 | 152.65 | 152.20 |
| RL of FL (m) | 151.80 / 152.45 (as printed) | 153 | |||||
| Cross slope | Plain | Plain | 1:12 | 1:10 | 1:11 | 1:11 | 1:13 |
| Gradient of road | 1:200 rising (up to 0+090) | 1:300 rising (0+090 onwards) |
Given data and assumptions
- Formation width of a dedicated four-lane road (NRS 2070): four lanes of 3.5 m, a 1.5 m median and two shoulders of 2.5 m give about 21.0 m; m is used (check with the standard in use).
- Side slope in embankment and in excavation (the question writes 1:2 and 1:1.5, i.e. 1 vertical to 2 and 1.5 horizontal). Cross slopes: "plain" is taken as level ground.
- The printed formation levels are unclear. Formation level at 0+000 is taken as 152.00 m, rising 1 in 200 up to 0+090 (152.45 m, as printed) and then 1 in 300 to 0+180 (152.75 m).
Method
Ground has a transverse (cross) slope (H:V), so each section is a side-hill section. With centre height (cutting +, filling −) above/below formation level, formation width and side slope :
Here are the horizontal distances of the up-hill and down-hill toes from the centre line and the heights of the ground above formation at the toes (formulas for cutting). For a section wholly in filling the roles swap: the down-hill toe is the far one, and , with the filling height and the filling slope. Where the ground line crosses the formation level inside the road width (part cutting, part filling), the cutting and filling areas are found separately from the co-ordinates of the section (toe points from the same intersection equations). Volume between sections = mean area × distance, taken separately for cutting and filling.
| Chainage | GL (m) | FL (m) | Depth of cutting / height of filling (m) |
|---|---|---|---|
| 0+000 | 152.000 | 152.000 | 0.000 |
| 0+030 | 152.350 | 152.150 | cutting 0.200 |
| 0+060 | 152.600 | 152.300 | cutting 0.300 |
| 0+090 | 152.800 | 152.450 | cutting 0.350 |
| 0+120 | 153.000 | 152.550 | cutting 0.450 |
| 0+150 | 152.650 | 152.650 | 0.000 |
| 0+180 | 152.200 | 152.750 | filling 0.550 |
Sectional areas
| Chainage | Centre ht. (m) | Cutting area (m²) | Filling area (m²) |
|---|---|---|---|
| 0+000 | 0.00 | 0.000 | 0.000 |
| 0+030 | cut 0.20 | 4.260 | 0.000 |
| 0+060 | cut 0.30 | 9.467 | 2.381 |
| 0+090 | cut 0.35 | 11.529 | 3.062 |
| 0+120 | cut 0.45 | 12.563 | 1.711 |
| 0+150 | 0.00 | 5.803 | 6.125 |
| 0+180 | fill 0.55 | 0.488 | 14.160 |
Working for one section:
Take chainage 0+060: centre cutting depth m, , m.
- Ground height above formation at the uphill edge m, at the downhill edge m.
- Toe of the side slope on the uphill side at m from the centre line (ground above formation by 1.343 m); downhill toe at m (ground below formation by 0.690 m).
- Area from the co-ordinates of the polygon: cutting m², filling m².
Volumes
| Between | Distance (m) | Cutting (m³) | Filling (m³) |
|---|---|---|---|
| 0+000 – 0+030 | 30.0 | 63.90 | 0.00 |
| 0+030 – 0+060 | 30.0 | 205.91 | 35.71 |
| 0+060 – 0+090 | 30.0 | 314.95 | 81.64 |
| 0+090 – 0+120 | 30.0 | 361.39 | 71.61 |
| 0+120 – 0+150 | 30.0 | 275.49 | 117.54 |
| 0+150 – 0+180 | 30.0 | 94.36 | 304.28 |
| Total | 180.0 | 1,315.99 | 610.78 |
Answer: Earthwork in cutting = 1,315.99 m³; earthwork in filling = 610.78 m³.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Hill road earthwork, chainage 130-280 · Estimating and Costing, chapter 6
- Hill road earthwork, chainage 12-15 · Estimating and Costing, chapter 6
- Hill road earthwork, chainage 0-150 (50 m) · Estimating and Costing, chapter 6
- Road earthwork, chainage 0-80 (s) · Estimating and Costing, chapter 6 · asked 2×
- Hill road earthwork, cutting 4 m / banking 6 m · Estimating and Costing, chapter 6
- Hill road earthwork, chainage 0-600 (12 marks) · Estimating and Costing, chapter 6
- Cutting volume, 60 m, GL 1181.50, formation 1179.00 · Surveying I, chapter 9 · asked 8×
- Embankment 1,00,000 m³ excavation · Soil Mechanics, chapter 2
- Cutting volume, 60 m, formation level 279.00 · Surveying I, chapter 9 · asked 7×
- Cutting volume, 60 m, formation level 278.00 · Surveying I, chapter 9 · asked 7×