- 2081 Bhadra · 4 marks
Minimum critical reservoir top elevation
Short answer
Using the broad-crested weir equation with effective length 61 m and Cd=0.6, the required head is 13.10 m. The minimum critical reservoir elevation is 1263.10 m.
Determine the minimum critical elevation of the top of the reservoir, which has a spillway with a maximum discharge capacity of 5127 m³/s. The spillway has five openings, each 12.2 m wide. The crest level of the spillway is 1250 m. Assume a discharge coefficient of 0.6 for the broad crested weir.
Given: m³/s; 5 openings, each 12.2 m wide; crest level 1250 m; for a broad-crested weir.
The minimum critical (maximum flood) level of the reservoir is the crest level plus the head that is needed to pass the maximum discharge.
Effective length
(Pier contraction is neglected, since no pier or abutment coefficient is given.)
Discharge equation (broad-crested weir)
Reservoir level
Answer: the top (flood) level of the reservoir must not be lower than 1263.10 m (head over the crest m).
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Gravity dam equilibrium and overtopping discharge coefficient · Hydropower Engineering, chapter 4
- Discharge through chute spillway ogee crest · Hydropower Engineering, chapter 4
- Minimum reservoir capacity and wasted water · Hydropower Engineering, chapter 3
- Phreatic line and discharge (crest 300 masl) · Hydropower Engineering, chapter 4 · asked 2×
- Uniform draw-off and reservoir capacity · Hydropower Engineering, chapter 3
- Installed capacity, energy and daily peaking reservoir (2079) · Hydropower Engineering, chapter 3 · asked 2×
- Reservoir routing through spillway, 6-hr inflow · Engineering Hydrology, chapter 7
- Crest level of fall, Q 30 m3/s · Irrigation and Drainage Engineering, chapter 7
- Weir waterway and crest levels, 16000 m3/s · Irrigation and Drainage Engineering, chapter 5
- Discharge over overflow spillway · Hydro Power, chapter 6