- 2075 Chaitra · 6 marks
Surge tank functions and formulas
Short answer
A surge tank reduces water hammer, acts as a reservoir for sudden flow changes, protects the tunnel and penstock, and improves governor stability. Max upsurge Zmax = V0 sqrt(L At/(g As)), max downsurge Zmin = -ΔV sqrt(L At/(g As)), oscillation period T = 2π sqrt(L As/(g At)), minimum area Ath = L At/(2g α (H0 - hf)).
What are the functions of a surge tank? Write down the formulas to calculate the maximum upsurge and downsurge, time of oscillation and minimum area of a surge tank with usual notations.
Functions of a surge tank
- Reduces water hammer: it reflects the pressure waves, so the long headrace tunnel is protected from high pressure rise or fall.
- Acts as a reservoir that supplies the extra water when the turbine discharge is suddenly increased, and absorbs the water when the discharge is suddenly cut off.
- Protects the tunnel from collapse and the penstock from over-pressure; reduces the length of the pipe in which the water hammer acts.
- Improves speed regulation of the turbine (governor stability) by letting the tunnel flow change slowly.
Formulas (simple cylindrical tank, usual notations)
= tunnel length, = tunnel area, = surge tank area, = initial velocity in the tunnel, = gravity, = friction loss at (), = gross head.
| Quantity | Formula |
|---|---|
| Max upsurge (full rejection, no friction) | |
| Max downsurge (sudden demand, no friction) | |
| Effect of friction | Friction damps the oscillation, so the upsurge and downsurge are smaller than these frictionless values; exact values are read from Jaeger's/Johnson's charts in terms of |
| Time period of oscillation | |
| Minimum area (Thoma stability) |
where . For a partial change of discharge, is replaced by the change in the tunnel velocity. The area of the tank is taken as 1.0-1.5 times (usually larger when the upsurge/downsurge governs the design).
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Surge tank area, up/downsurge, invert level · Hydropower Engineering, chapter 6
- Derive minimum upsurge without damping · Hydropower Engineering, chapter 6
- Surge tank: tunnel 5 m dia, 28 cumec · Hydropower Engineering, chapter 6
- Surge and water hammer: 25 m³/s, 15 m surge tank · Hydropower Engineering, chapter 6 · asked 3×
- Surge and water hammer: 45 m³/s, 20 m surge tank · Hydropower Engineering, chapter 6 · asked 2×
- Surge and water hammer: 60 m³/s, 30 m surge tank · Hydropower Engineering, chapter 6 · asked 2×
- Surge tank functions and design criteria · Hydro Power, chapter 5 · asked 2×
- Functions of a surge tank · Hydraulics, chapter 4 · asked 2×
- Maximum demand and need to calculate it · Industrial Power Distribution and Illumination, chapter 1