Primary/secondary energy and pondage volume

Short answer

Primary energy is 1375 GWh/yr, secondary 11,217 GWh/yr. Power per unit flow: 1569.6 Q kW. For firm capacity increased by 150% (to 250 m³/s), pondage required is 1.025×10^9 m³.

Determine the primary and secondary energy if the hydrograph as shown below is given net head = 200 m and efficiency = 80%. What is the volume of the pondage required if the firm capacity is increased by 150%.

MonthJanFebMarAprMayJunJulyAugSeptOctNovDec
Discharge (m³/s)1001201403003201800200025102000900500300

Primary energy is produced by the minimum flow that is available all year; secondary energy is produced by the flow above this minimum. No design discharge is given, so the plant is assumed to use all the river flow (secondary energy is then the maximum possible). Each month is taken as 730 h (2.628×1062.628 \times 10^6 s).

Power per unit discharge

P=9.81×Q×200×0.80=1569.6 Q kWP = 9.81 \times Q \times 200 \times 0.80 = 1569.6\,Q\ \text{kW}

Primary energy

Minimum flow = 100 m³/s (January).

Pf=1569.6×100=156,960 kW=156.96 MWEp=156,960×8760=1374.97 GWh\begin{aligned} P_f &= 1569.6 \times 100 = 156{,}960\ \text{kW} = 156.96\ \text{MW} \\ E_p &= 156{,}960 \times 8760 = 1374.97\ \text{GWh} \end{aligned}

Total and secondary energy

MonthQ (m³/s)Power (MW)Energy (GWh)
Jan100156.96114.58
Feb120188.35137.50
Mar140219.74160.41
Apr300470.88343.74
May320502.27366.66
Jun18002825.282062.45
Jul20003139.202291.62
Aug25103939.702875.98
Sep20003139.202291.62
Oct9001412.641031.23
Nov500784.80572.90
Dec300470.88343.74
Total10,99012,592.43
Es=12,592.43−1374.97=11,217.46 GWhE_s = 12{,}592.43 - 1374.97 = 11{,}217.46\ \text{GWh}

Pondage for firm capacity increased by 150%

"Increased by 150%" is read as new firm capacity = 1+1.5=2.51 + 1.5 = 2.5 times the original.

Pf,new=2.5×156.96=392.4 MWQf,new=2.5×100=250 m3/s\begin{aligned} P_{f,new} &= 2.5 \times 156.96 = 392.4\ \text{MW} \\ Q_{f,new} &= 2.5 \times 100 = 250\ \text{m}^3/\text{s} \end{aligned}

Months with flow below 250 m³/s must be supplied from storage:

MonthQDeficit (250 − Q)
Jan100150
Feb120130
Mar140110
Total390 m³/s-month
V=390×2.628×106=1.025×109 m3\begin{aligned} V &= 390 \times 2.628\times10^6 \\ &= 1.025 \times 10^9\ \text{m}^3 \end{aligned}

This storage is easily refilled in the monsoon months, when flows are far above 250 m³/s.

Answer: Primary energy ≈ 1375.0 GWh/yr; secondary energy ≈ 11,217.5 GWh/yr; storage (pondage) required ≈ 1.025 × 10⁹ m³ (1025 million m³).

(If "increased by 150%" is taken as 1.5 times, i.e. firm flow 150 m³/s, the deficits are 50 + 30 + 10 = 90 m³/s-month and the storage is 90×2.628×106=2.37×10890 \times 2.628\times10^6 = 2.37\times10^8 m³.)